Council archive · source document

Engineering Services Assessment · MCU15/0122

Attached to the e-mail MCU15/0122 Development Application - Engineering Services Assessment Email 5 of 5.

of 57

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (10.3 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Original PDF page 20, section 1. The text section number identifies this passage in the reader.

Earthworks Code – The Noosa Plan
Performance Criteria and Acceptable Solutions

Performance outcomes                                    Acceptable outcomes                               Assessment

Drainage                                                S1.1                                              RO1 Bulk earthworks will be designed to prevent
O1                                                      The finished surface gradient of any filled or        ponding on the site or on neighbouring land.
                                                        excavated area is within the range 0.5% to
Finished surface levels ensure land is free draining.
                                                        1.5% and drains to Council’s stormwater
                                                        infrastructure where available or where
                                                        stormwater infrastructure is not available,
                                                        toward the street.
Hydraulics                                              No solution provided.                             RO2 The existing drainage characteristics of the site
O2                                                                                                            and surrounding area has been considered. The
                                                                                                              proposal ensures that surrounding properties
Any change to the level of the land does not have an                                                          and downstream stormwater infrastructure and
adverse flooding impact on the flooding and drainage                                                          waterways are not adversely impacted by the
characteristics off-site.                                                                                     proposed development.


Geotechnical considerations                             For assessable development—                       RO3 All filling will be undertaken in accordance with
O3                                                      S3.1    Filling works are undertaken in               Council’s PSP5 – Engineering Design
                                                                                                              Standards – Roads and Drainage & Earthworks
Earthworks do not result in geotechnical instability on accordance with Section 2.8- Filling of Site of
                                                        Council’s PSP5 - Engineering Design                   and AS 3798 - Guidelines for earthworks on
the premises or nearby premises.
                                                        Standards- Roads and Drainage & Earthworks            commercial & residential development. All
                                                                                                              excavation will be undertaken with no adverse
                                                        AND
                                                                                                              impact on neighbouring properties or
                                                        S3.2 W here the filling is for residential            surrounding infrastructure.
                                                        commercial or industrial purposes the works
                                                        comply with Sections 3 to 6 of AS 3798 -
                                                        Guidelines for earthworks on commercial &
                                                        residential development.


Local amenity                                         S4.1 The following control measures are             RO4 Water trucks shall be used to minimise dust
O4                                                    implemented—                                            emissions. An ESC plan is to be prepared for
Earthworks do not cause disturbance to the amenity of a) regular water spraying of exposed areas to           the construction phase.
the neighbouring land.                                suppress dust;

Used in these records

About this file

File size
10.3 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Engineering Services Assessment.pdf · 10.3 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.