Attachment E - Stormwater Management Report · MCU24/0112
Very large file (21.8 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
• ≥ 60 % reduction in total phosphorus load (TP)
• ≥ 45 % reduction in total nitrogen load (TN)
• ≥ 90 % reduction in gross pollutant load
Pollutants typically generated during the operational phase of the development include:
• Litter/gross pollutants;
• Sediment;
• Nutrients (N & P);
• Hydrocarbons (oils and grease); and
• Heavy metals.
Stormwater treatment measures are shown on the attached stormwater management drawings and
include:
• ATLAN FIL.30-EMC-M Filter system to be installed within the proposed combined treatment
tank within development site for final treatment of stormwater prior to discharging to the
stormwater network.
Stormwater modelling has been carried out using MUSIC modelling software to determine the required
infrastructure needed to meet the Water Quality Objectives (WQO’s) above.
4. 2 MU S IC M od el
MUSIC modelling for this development has been carried out using MUSIC Version 6.4 and rainfall data
obtained from the pluviograph tool on the eWATER website for Cooroy Composite. The developed site
catchment and treatment measure details included in the MUSIC model are outlined in Table 1.
Table 1 – MUSIC model parameters
Description Specification
Assumed road catchment to filter system 0.0368 Ha (100% impervious)
Assumed roof catchment to filter system 0.1084 Ha (100% impervious)
Assumed ground catchment to filter system 0.1140 Ha (30% impervious)
Assumed ground catchment bypassing filter 0.0066 Ha (19% impervious)
system
Assumed road catchment bypassing filter 0.0008 Ha (100% impervious)
system
Assumed access path bypassing filter system 0.0058 Ha (100% impervious)
and discharging from site via swale drain
Number of modelled ATLAN Filters 8
The MUSIC model layout is shown in Figure 2.
3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment E - Stormwater Management Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 21.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.