       Response:

       The originally submitted vehicle swept path analysis drawings prepared by TTM have been updated
       and are presented in Appendix B of the traffic report. These drawings demonstrate that all aspects
       of proposed development layout adequately accommodate the relevant design vehicles access,
       circulation and manoeuvring.

Item 10:

       There will be a demand for customers to use both centres in the same trip and for this reason there
       should be integration between the two buildings for cars, pedestrians and service vehicles.

       Provide amended plans that address and provide for the following:

           a) Redesign the proposal to integrate the vehicular access arrangements (car and service
              vehicle) and pedestrian connectivity of the proposed Bunnings expansion with the existing
              Bunnings development.
           b) Demonstrate how vehicles would safely and appropriately exit the existing northern Bunnings
              access driveway and then enter the proposed new Bunnings expansion driveway.
           c) Quantify and justify the loss of on-street parking arising from the proposed access
              arrangements.
           d) Demonstrate that a delivery vehicle entering the new driveway will have adequate height
              clearance where it passes under the new building.
           e) Justify one-way operation of the proposed basement carpark when the preferred two-way
              operation can be readily accommodated.

       Response:

       a) Integration of the two sites is not physically possible due to the substantial level difference
          between the two sites being approximately 3m.

           It is acknowledged that there may be some shared trips between the existing Bunnings
           warehouse site and the proposed development, however anecdotally, perhaps in the order of
           20-30% of trips to the proposed development would also attend the existing development. This
           equates to around 2-3 trips during the weekday peak hour periods and 3-5 trips during the
           weekend peak hours.

       b) TTM drawing number 21BRT0226-04B (Appendix B of the traffic report) demonstrates that the
          design customer vehicle (large car and dual-axle trailer combination) can safely and adequately
          exit the existing Bunnings northern access on Gateway Drive, enter the central right turn lane
          standing clear of both southbound and northbound through lanes, and enter the proposed
          southern access for the development site. Importantly, the analysis of the right turn lane



                                                                                                             2

Used in these records

About this file

File size
15.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment D - Traffic Response.pdf · 15.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.