                                                                       DANYA COOK TOWN PLANNING

Applicant’s Response

In response to Item 6 of Council’s Information Request, please refer to the supplementary Engineering Plans prepared by Rienmac
Pty Ltd included at Appendix B, which indicate the garage door openings and provision for a B99 vehicle, as described in
AS/NZS2890.1:2004

Issue

Council has some concerns with the transitions from the proposed driveway to the adjoining sections of footpath.

Information Required

Item 7

7.      Provide additional detail on the extent of works required to smoothly transition from the proposed driveway to the adjoining
        sections of footpath.

Applicant’s Response

In response to Item 7 of Council’s Information Request, please refer to the supplementary Engineering Plans prepared by Rienmac
Pty Ltd included at Appendix B, which provide additional detail on the extent of works required to smoothly transition from the
proposed driveway to the adjoining sections of footpath.

Issue

It is expected that the proposed development will need to include changes/additions to the existing stormwater drainage system, but
no detail has been provided.

Information Required

Item 8

8.      Provide a plan of the existing stormwater drainage system and indicate any additions/improvements necessary to comply with
        current standards. Please note that the system must be in accordance with The Noosa Plan 2020 – Water Quality and Drainage
        Code and include climate change considerations (Performance Outcome PO2 and Acceptable Outcome AO2.4 (a 20% increase
        in rainfall intensity by 2100.)

Applicant’s Response

In response to Item 8 of Council’s Information Request, supplementary Engineering Plans prepared by Rienmac Pty Ltd included at
Appendix B, which includes details with respect to the existing stormwater drainage system and indicates any
additions/improvements necessary to comply with current standards.

3.0        SUMMARY

In accordance with Section 13.2 of the Development Assessment Rules, we hereby provide Council with a response to all of the
information requested and ask that Council proceed with the assessment of the development application. We trust Council will issue
a favourable Development Permit in due course and should Council have any questions with respect to the above, please do not
hesitate to contact me direct.

Kind regards,




Danya Cook B.Urb.Reg.Plan
Director / Principal Town Planner
M: 0422 051 263
E: [email protected]
                                                                  4


Response to Council’s Information Request                                                                              February 2022
Log in to download the original file

Response to Council's Information Request.pdf · 8.2 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.