Decision Notice - Council Meeting Decision - MCU22 0051 [As Published] · MCU22/0051

of 12

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                        b.      Pedestrian pathways between the proposed car parking area and the building/s.
                        c.      Adequate separation of all specific pedestrian routes from vehicle access and
                                manoeuvring areas, and clear demarcation by pavement marking, signposts or
                                changes in surface materials or levels.
                        d.      Signage and lighting at strategic locations to direct people to building entries and
                                public toilet facilities.
                        e.      Pedestrian refuge areas at strategic locations within the carpark to ensure safe
                                and convenient congregating of pedestrians waiting to cross major access
                                driveways.
                        f.      A total of 2 bicycle parking spaces
                        g.      End of trip facilities involving 2 lockers, male and female showers and change
                                rooms.
                        Condition 28a is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
                        infrastructure.
                 STORMWATER DRAINAGE
                 29.    Carry out the development to ensure that adjoining properties, reserves and roads are
                        protected from ponding or nuisance from stormwater as a result of any works
                        undertaken.
                 30.    The site must be provided with a stormwater drainage system connecting to a lawful point
                        of discharge. The works must be undertaken in accordance with an Operational Works
                        approval, AS3500.3 and the Queensland Urban Drainage Manual, and must include in
                        particular:
                        a.      Underground detention tanks and drainage works generally as shown in Appendix
                                C of the Site Based Stormwater Management Plan Rev 07, prepared by ACOR
                                Consultants, dated 24/08/2023
                        b.      Collection and discharge of stormwater to Council’s underground pipe network in
                                Gateway Drive
                        c.      Extension of the site stormwater system to accommodate stormwater from the
                                external catchment East of the site, including registration of drainage easements
                                over the pipe network within the subject site in favour of the upstream lot.
                        d.      Cut off drains along the Eastern site boundary to convey external catchment flows
                                up to the 1%AEP climate change event into the pipe network within the site
                        e.      The use of gravity stormwater drainage and not surcharge pits.
                        Condition 30 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
                        infrastructure.
                 STORMWATER QUALITY MANAGEMENT
                 31.    A stormwater quality treatment system must be provided for the development. The works
                        must be undertaken in accordance with an Operational Works approval and the
                        Bioretention Technical Design Guidelines (Water by Design, 2014), and must include in
                        particular:
                        a.      Stormwater quality treatment devices of a size and location generally in
                                accordance with those shown in Appendix C of the Site Based Stormwater
                                Management Plan Rev 07, prepared by ACOR Consultants, dated 24/08/2023
                        b.      A minimum 5kL rainwater harvesting tank, plumbed to supply toilet flushing and
                                landscape irrigation
                        c.      Bioretention devices which:
                                i.     Are designed generally in accordance with IPWEAQ Standard Drawing No.
                                       DS- 073.




                                                                                                          Page 6 of 12
Document Set ID: 22640657
Version: 7, Version Date: 02/11/2023

Used in these records

About this file

File size
181 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Council Meeting Decision - MCU22 0051 [As Published].pdf · 181 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.