Construction communications
A construction communications plan was designed collaboratively by TNC and NC. The plan outlined the key activities that
were to be undertaken to ensure the Noosa community were well informed of the construction works. The plan included
public notices, special information sheets, letterbox drops and visits to affected households businesses.
The letterbox drops were undertaken in two stages: Late July 2022 for the business and residents close to the load out site
on Hilton Esplanade, and early August 2022 for the residents of the Noosa Sound that could be affected by the construction
activities at Noosa Sound East and West restoration sites.
Few residents on Witta Circuit and Mossman Court were home, when visited, but those that were expressed for the project
with comments such as “It’s about time.” and “I’m glad it’s not a walkway.” All affected households received an information
pack and contact information for TNC.
Table 6 chronicles the construction communication actions undertaken.
Table 6: Chronology of construction communication actions undertaken
Timing Audience Comms tool Key messages Notes / reasoning Lead
Tues Partners and Oyster Construction update Updated staff from agencies TNC
19/7/22 stakeholders chronicle Project update close to the project as well as
newsletter funding bodies and interested
individuals
Tue or Affected Letter drop Project overview The residents of Hilton TNC
Wed 19 residents What to expect - Esplanade, Witta Circuit,
or construction Mossman Court and the Lakes
20/7/22 Who to contact Resort directly in eyesight and
earshot of construction
activities.
Friday Noosa Notice in Timing of construction Requirement of Reef Builder TNC
22/7/22 Community Newspaper Official notice Grant
(Noosa Today)
Friday Noosa Council Project overview This sits on the NC Works in NC
22/7/22 Ratepayers Construction Locations of activities Progress (WIP) page with other
Noosa News – works in Expected construction local construction activities.
Community progress page activities
on Content developed by TNC.
NC website
Friday Noosa Media Release Construction Went to media on 2 August. TNC
29/7/22 Community started/starting Delayed due to CEMP.
Broader Quotes from all funding
Audience partners
Starting Broader TNC Social Media Noosa build has started Celebrate the build starting. TNC
week Audience Project overview Why Oyster Reefs are
1/8/22 Australia and important ecosystems.
World
Starting QLD Targeted Reef build has begun Some already lined up, some TNC
week Australia interviews – Noosa leading the way in will arise from of the media
1/8/22 ABC radio, local Reef Building in QLD release.
news
36
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.