2022-10-24 General Committee Meeting- Item 7 - Attachment 1 - Noosa Oyster Ecosystem Restoration Project - Final Report (1)

of 73

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Construction
Key activities under the construction phase are outlined below:

 Quarry selection

 Boral (Moi Pocket), Sunshine Coast Quarries (Nambour) and
 Caldwell’s Quarry at Kin Kin were inspected and assessed by
 TNC.

 Boral Moy Pocket was eventually selected as the preferred
 quarry to supply the 3250 tonnes of local, igneous rock to
 the Project.



                                                                  Figure 22: Craig Bohm (TNC) – left and Jay Maateenz (M&J)
                                                                  – middle, visit the Boral Moy Pocket Quarry. Photo by C Bohm

 Construction contractor selection

 TNC selected M&J Marine Services as the preferred
 construction contractor. M&J Marine Services was the only
 company that tendered for the work with experience
 restoring intertidal oyster reefs. The company had
 developed specialty equipment (such as a light-weight barge
 and loading systems) for this kind of work.

 The company also offered its services at a competitive price
 and delivered above and beyond the contract costs.

                                                                  Figure 23: M&J Marine Services signage and screens at the
                                                                  load out site. Photo by C Bohm.

 Load Out Site establishment

 TNC and NC selected the unofficial boat ramp at the end of
 Hilton Esplanade, Noosaville, as the Project’s load out site.

 This boat ramp is regularly used by private companies, which
 use the ramp on an ad hoc and unregulated basis to launch
 and retrieve large vessels. Heavy machinery such as low
 loader semi-trailers and large cranes regularly frequent the
 ramp.

                                                                  Figure 24: Load out site looking down river. Photo by C Bohm




                                                                                                                                 58
Log in to download the original file

2022-10-24 General Committee Meeting- Item 7 - Attachment 1 - Noosa Oyster Ecosystem Restoration Project - Final Report (1)(PDF, 8MB).pdf · 8.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.