Att 3 - SDAP compliance

Attached to the e-mail Retail Bus Type 2 Shop & Salon, Multiple Housing Type 4 Conventional (2 units) & Boundary Realignment (3 lots into 3) - MCU18/0158 & RAL18/0017.

of 19

Page text shows just the words. Original shows the document exactly as it was published.

 Performance outcomes                                      Acceptable outcomes                                   Response
                                                           AO32.5 Land is able to be reinstated to the pre-
                                                           development condition at the completion of the
                                                           use.
 PO33 Vehicular access to a future state-                  AO33.1 Development does not require new or            N/A
 controlled road is located and designed to not            changed access between the premises and a
 create a safety hazard for users of a future state-       future state-controlled road.
 controlled road or result in a worsening of               AND
 operating conditions on a future state-controlled         AO33.2 Vehicular access for the development is        N/A
 road.                                                     consistent with the function and design of the
                                                           future state-controlled road.
 Note: Where a new or changed access between the
 premises and a future state-controlled road is
 proposed, the Department of Transport and Main
 Roads will need to assess the proposal to determine
 if the vehicular access for the development is safe. An
 assessment can be made by Department of Transport
 and Main Roads as part of the development
 assessment process and a decision under section 62
 of Transport Infrastructure Act 1994 issued where
 sufficient information is provided.
 PO34 Filling, excavation, building foundations            No acceptable outcome is prescribed.                  N/A
 and retaining structures do not undermine, or
 cause subsidence of, a future state-controlled
 road.

 Note: To demonstrate compliance with this
 performance outcome, it is recommended that an
 RPEQ certified geotechnical assessment is provided,
 prepared in accordance with volume 3 of the Road
 planning and design manual, 2nd edition, Department
 of Transport and Main Roads, 2016.
 PO35 Fill material from a development site does           AO35.1 Fill material is free of contaminants          N/A
 not result in contamination of land for a future          including acid sulfate content.
 state-controlled road.
                                                           Note: Soil and rocks should be tested in accordance
                                                           with AS1289 – Methods of testing soils for
                                                           engineering purposes and AS4133 2005 – Methods of
State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                            Page 18 of 19
Log in to download the original file

Att 3 - SDAP compliance.pdf · 174 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.