20080490 - Decision Notice [As Published] · 112008.490
Project Job No. 90775
SERVICE PENETRATIONS
CLASS | LAGGING THICKNESS (7)
vit S,M 25
H,E, F
i t 40
Slab Surface
Not Allowed J Not Allowed DIS FE siap Mesh
Allowed 0 Q Pipe & Lagging Allowed - Jo dvd © Pipe & Lagging
, nominated footing
Refer detail § Q de Refer detail
pth must be T
below == maintained below _P&low On | oO Y _ Trench Mesh
pipe
Allowed § 3 Altowed O
Footing must not be jackhammered for
placement of pipes
WHEN SERVICE PENETRATION PASSES THROUGH FOOTINGS OR THICKENINGS
normal EDGE BEAM SLAB THICKENING
footing . L. }
depth SS SOOT
7
mol v3 & -[Ty 3
= extra depth vy ~~ Ft
t fe 75 mm min. from bottom reinforcement——__—_——_-_-—_
Slab Thickening depth must not be
extra depth Reinforcement duced for pi
reduced for pipes.
NOTE - Specified footing and slab thickening depth and cover requirements must be maintained.
Where service pipe interferes with cover to steel or concrete depths the footing must be locally deepened as
shown below,
Particular attention should be paid to the provision of flexible service connections as detailed in AS 3500
"The National Plumbing and Drainage Code - 1996” on all class H and E sites.
LOCAL DEEPENING SS —————————
TH slab mesh
trench mesh 75 mm min.extra depth required. zl Site
[ M Classification
~ LA : “My”
t Mw OS ee .
q f j
1000 mm, |. 1000 mm
50 mm pit >|
THE FOLLOWING PRACTICES ARE NOT PERMITTED.
Cutting the reinforcement steel to go around the pipe
Bending the reinforcement steel to go over the pipe
SPECIAL REQUIREMENTS FOR SITE CLASSIFICATIONS "H", "E"& "P"
OPTIONS FOR SEWER DRAINAGE LAYOUT PIPE PENETRATIONS on . 4
EDGE BEAM
Swivel Joint ( 4... wet
Only required when
Class "E" ——>
My wae mK Slip Coupling
3 |
Lt
L 75 mm miri.
Expandable Joint coupling set
at mid-setting to allow both
upward and downward movement
(This may be deleted on Class 'H’ sites)
(a) Stip Couplings are nat required where
pipe work is strapped to slab steel
(b) Slip Couplings may be substituted for
expansion joints on 'P' sites
Service Pipe
Stip Couplings
EDGE BEAM
Expansion Joint
Coupling
Expansion Joint =
Coupling |
Slip Coupling Ny
Possibly piered
Expansion Joint
Coupling
Note : Slip coupling may be removed
where connection point is within 500mm
of edge beam/ slab edge
Slip Couplings
Elevation
Service Pipe
Expandable Joints & Swivel Joint Specifications
Site Classification Minimum Expansion of Joints Swivel Joint
Class "H" 80mm +or- 15° Allowable Rotation
Class “E" 150mm +or-15° Allowable Rotation
Class “P" 80mm + or- 15° Allowable Rotation
Class "M" 25mm lagging through footing Not Applicable
Joints and Swivels are to be manufactured and comply with AS1260 and AS1415.
Joints and Swivels are to be installed as per manufactures specificationes.and inspected by the Local Authority. |
Sewer pipes founded within the filled section of the building pad under the slab are to be hung from slab reinforcement with metal straps.
Note: These details are to be used as a guide only. Where it is a requirement of the relevant Local Authority for these detaifs to b
adhered to, any variations or modifications shall be dircted at the Local Authority as per AS2870-1996 Section 5.5.4 clause (d).
Page 4 of 5
Design Company
SOILTEST AUSTRALIA ENGINEERING SERVICES PTY LTD
Suite 1, 848 Boundary Rd, Richlands, Qid, 4077
ACN 109 233 123 Fax (07) 33759299 Ph.1300 731523
SIA Builder
Diane Jones & Don Cielland
ALLIANCE
575 Black Mountain Road, Cooroy Ald 4563
Builders Client
NIA
Client Order Number. N/A
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
20080490 - Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 2.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.