OPW 15-0099 RFI Response combined scan

Attached to the e-mail OPW15/0099 - Information Request Response.

of 12

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Calibre Consulting (Aust) Pty Ltd
Ground Floor, 545 Queen Street
Brisbane QLD 4000

PO Box 10349 Adelaide Street a
Brisbane QLD 4000 calibre
T +61 7 3895 3444

ABN 55 070 683 037 ak

Our Ref: 15-001261CL01.RB.rb
Your Ref: OPW15/0099
Contact: Monkeith Kadhum

3 August 2015

Noosa Council
PO Box 141
TEWAINTIN QLD 4565

Attention: Monkeith Kadhum

Dear Monkeith
Subject: 19 Trading Post Road, Cooroy - Response to Information Request OPW 15/0099

| refer to your information request correspondence dated 7 July 2015, regarding the development permit for operational
work (Bulk Earthworks) for the proposed development located at 19 Trading Post Road, Cooroy. Below is our responses
to the items raised in the above correspondence.

Item 1

Issue: Condition 72 of the higher order approval requires a Stormwater Management Construction and Maintenance Plan
(SMCMP) to be approved by the Council’s CEO or delegated officer prior to issue of any Operational Works Approval.
This must be provided prior to issue of an Operational Works Approval.

Response:

The SMCMP addresses the ultimate water quality treatment devices. The WSUD is being undertaken with the roadworks
and drainage design and will be provided for the Roadworks and Drainage OPW application. We respectfully request
that the SMCMP be conditioned to be provided to Noosa Council with the Roadworks and Drainage OPW application.

Item 2

Issue: Condition 90 of the higher order approval requires plans detailing the methods of controlling erosion and sediment
to be submitted to the Council for approval prior to obtaining a Development Permit for Operational Works. The provided
Erosion and Sediment Control Plans are not reflective of the Approved Staging Plan, do not indicate how Specific
Outcomes O01 and O2 of the Noosa Plan Erosion and Sediment Control Code will be achieved with the proposed cut to fill
strategy and do not provide sufficient information to demonstrate how compliance with the State Policy for Water Quality
is possible.

Response:
Amended Erosion and Sediment control plans have been attached

a) The construction sequence/staging has been detailed on Calibre drawing 15-001261-113. The stabilisation of
the defined Future Aged Care Development (Shown as Stage 1B on approved plan CO-000-2014 Sheet 02 of
02, dated 02/02/15), will occur immediately after respreading of the topsoil. Our Client is proposing to
commence building works of the retirement village building in stage 1A and 2 within 2 months of completion of
the bulk earthworks and civil works. Stage 3 would be topsoiled and stabilised, if building works have not
commence within 12 months of completion of stage 1A civil works.

callbreconsulting.co
Log in to download the original file

OPW 15-0099 RFI Response combined scan.pdf · 1.1 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.