OZCARE NOOSA AGED CARE RESIDENCE                                                              Construction Management Plan


    Normal Control Measures

         a) Install and maintain filter mediums as required. Systems such as, silt sediment fencing, cover
            existing stormwater drain inlets with sediment screening and other appropriate bunding as
            required.
         b) Sediment control screening will be installed to site boundaries where site ground levels are higher
            than adjoining footpaths and neighboring land.
         c) Stormwater control, collection and treatment devices to be implemented if found to be necessary.
         d) Inspect and monitor stormwater manholes and waterways.
         e) Daily inspections will be undertaken to monitor and review the need for cleaning of footpath and
            roadway. Should the need arise the roads will be swept and cleaned by mechanical sweeping plant.
         f) Ensure safe storage of chemicals on site.
         g) Store all goods and materials in a manner to avoid contamination of water or areas where water
            may drain.
         h) Provide and inspect regularly readily accessible spill kits /pollution control equipment.
         i) Inspect regularly and remove / replace as required sediment control devices.
         j) Provide and maintain paint washout facilities to ensure that residual paint will not flow or be
            washed into any street gutters, stormwater drains or natural water ways.
         k) Refueling or the maintenance of vehicles or plant will take place in areas from which fuel, oils or
            washings will not be discharged into any street gutters, stormwater drains or natural water ways.

    8       PEDESTRIAN AND PUBLIC SAFETY ISSUES
    Site construction access will be via Cooyar Street. Appropriate traffic control will be provided if required,
    to attend to major deliveries, Concrete Pours and Crane Lifting to maintain vehicular and public safety
    around the site.

    Temporary Fencing / hoarding will be provided on the around the fire trail and works stages for public
    safety. The boundaries will be fenced as required.

         8.1        Site Main Access
    The main site construction pedestrian and vehicle access will be via the facilities Cooyar Street entry, into
    the facility and site area.

    All visitors entering the construction site must first report to the Project Site Office to sign in. There will
    be no Visitor Parking on site. While we do not envisage any requirement for traffic control, it will be
    provided if required for any activity identified.




Woollam Constructions                                                                                                 Page 9 of 17

Used in these records

About this file

File size
7.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Management Plan from STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdf · 7.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.