OZCARE NOOSA AGED CARE RESIDENCE Construction Management Plan
The proposed forms of construction and elements of the project will include but not be limited to the
following activities;
Prior to Operational and Site Works commencing onsite, ensure the following is complete and approvals
and permits have been received.
• A completed and distributed Dilapidation report of nearby infrastructure to all stakeholders.
• A Vegetation Management Plan and attend a pre-start meeting with council as per DA condition
requirements.
• The Engagement of a licensed fauna spotter catcher (qualified by the relevant QLD state
government authority) to manage the protection and relocation of any fauna. Submission to
Development services certification from the licensed Fauna Spotter Catcher that site has been
fully inspected and necessary protection/relocation measures and procedures are in place. All as
per DA Conditions.
• Natural Assets Local Law (NALL) permit as per DA requirements.
• Approved Site Drainage drawings and engineering calculations as per DA requirements.
• An approved Erosion and Sediment Control (ESC) Plan(s) and attend a pre-start meeting with
council as per DA conditions.
• Architectural drawings have been submitted for approval to Development Services as per DA
conditions.
• Landscape drawings have been submitted for approval to Development Services as per DA
conditions.
• Attend a Construction Management Plan (CMP) pre-start meeting with Council as per DA
conditions.
Enabling Works
• Preparation of a construction trafficable surface to the existing fire trail to the rear of the
facility.
• Client Decant Works.
• Installation and erection of site accommodation, hoarding/fencing, environmental controls,
temp services.
• Tree & Vegetation Removal.
• Implement any traffic management requirements as required from CMP meeting.
Refurbishment Works – Existing Acacia Building
• Client Decant Works
• Establish stage boundary and setup temporary fencing and hoardings.
• Isolate services.
• Complete internal and external demolition works.
• Complete new structural works internal & external to building.
• Installation of new facades and screens.
• Internal fit out and finishing works.
• Complete landscaping works.
All Stages - Stage Establishment / Demolition / Bulk Earthworks
• Client Decant Works
• Establish stage boundary’s and setup temporary fencing and hoardings.
• Pothole and survey the location of existing services as required and identified on project
drawings.
Woollam Constructions Page 4 of 17
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Management Plan from STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.