OZCARE NOOSA AGED CARE RESIDENCE                                                           Construction Management Plan


    1        INTRODUCTION
    T.F. Woollam & Son Pty Ltd trading as Woollam Constructions will be the Principal Contractor for the
    Construction and refurbishment works at Ozcare Noosa, 80 Cooyar Street, Noosa Heads, QLD. The plan
    outlines the management processes which will be implemented to ensure the interface of the
    construction works and adjoining areas is completed in an organised and safe manner and in accordance
    with the Development Approval.

    This Construction Management Plan (CMP) is to be read in conjunction with the following documents:

    Note: These reports will be finalised and inserted into the CMP prior to mobilisation.

         a) WHS Management Plan (WHSMP);
         b) Environmental Management Plan (EMP);
         c) Site Quality Plan.



    2        PROJECT SUMMARY
    The Ozcare Noosa project comprises of 4 stages of works across the site.

    Stage 1

         •     The demolition of existing single storey Banksia South building and the construction of a new 40
               bed two storey building with central servery/dining/sitting areas.
    Stage 2

         •     The demolition of the existing single storey Banksia North building and some of the existing back
               of house areas and the construction of a new 30 bed two storey building with central
               servery/dining/sitting areas.
         •     The construction of a new kitchen, laundry and other primary BOH service rooms.
         •     Construction of the new Administration Area.
         •     Construction of a new link to the existing Acacia Building.
         •     Refurbishment of the existing Acacia Building.
         •     The existing Administration area will remain in operation for the remaining stages.
    Stage 3

    Demolition of the existing Casuarina accommodation building and construction of a new Communal
    Areas building which ties into the new Administration Area.

    Stage 4

         •     Demolition of the existing Administration building and extension of the existing road turn around
               and car parking. Works will also include a new Porte Cochre and link to the new Banksia South
               building.

         2.1        Construction



Woollam Constructions                                                                                              Page 3 of 17

Used in these records

About this file

File size
7.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Management Plan from STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdf · 7.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.