OZCARE NOOSA AGED CARE RESIDENCE Construction Management Plan
1 INTRODUCTION
T.F. Woollam & Son Pty Ltd trading as Woollam Constructions will be the Principal Contractor for the
Construction and refurbishment works at Ozcare Noosa, 80 Cooyar Street, Noosa Heads, QLD. The plan
outlines the management processes which will be implemented to ensure the interface of the
construction works and adjoining areas is completed in an organised and safe manner and in accordance
with the Development Approval.
This Construction Management Plan (CMP) is to be read in conjunction with the following documents:
Note: These reports will be finalised and inserted into the CMP prior to mobilisation.
a) WHS Management Plan (WHSMP);
b) Environmental Management Plan (EMP);
c) Site Quality Plan.
2 PROJECT SUMMARY
The Ozcare Noosa project comprises of 4 stages of works across the site.
Stage 1
• The demolition of existing single storey Banksia South building and the construction of a new 40
bed two storey building with central servery/dining/sitting areas.
Stage 2
• The demolition of the existing single storey Banksia North building and some of the existing back
of house areas and the construction of a new 30 bed two storey building with central
servery/dining/sitting areas.
• The construction of a new kitchen, laundry and other primary BOH service rooms.
• Construction of the new Administration Area.
• Construction of a new link to the existing Acacia Building.
• Refurbishment of the existing Acacia Building.
• The existing Administration area will remain in operation for the remaining stages.
Stage 3
Demolition of the existing Casuarina accommodation building and construction of a new Communal
Areas building which ties into the new Administration Area.
Stage 4
• Demolition of the existing Administration building and extension of the existing road turn around
and car parking. Works will also include a new Porte Cochre and link to the new Banksia South
building.
2.1 Construction
Woollam Constructions Page 3 of 17
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Management Plan from STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.