Approved Decision Notice - DBW25 0023 (As Published)

of 5

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                     Officer:            Andrew Gaffney
                                                                                     Direct Telephone:   07 5329 6284
                                                                                     Our Reference:      DBW25/0023
                                                                                     Your Reference:     n/a

               16 April 2025


               Aus Garage Pty Ltd
               C/- Project BA
               PO Box 45
               NOOSAVILLE QLD 4567
               [email protected]



               Dear Sir/Madam,
                                                         Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 10 April 2025, Council decided to approve the
               application, subject to conditions.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              DBW25/0023

                   Street address:              837 McKinnon Drive, COOROIBAH QLD 4565

                   Real property description:   Lot 13 RP 181841

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Building Work Assessable Against the Planning Scheme -
                       Additions to Dwelling House (shed) – Total gross floor area & Roofed Area more than
                       500m²
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

                       When Conditions must be Complied With
               1.      Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                       the use of the building commencing, and then compliance maintained at all times while the
                       use continues.




               ABN 97.969.214.121                                                                PO Box 141
               noosa.qld.gov.au                                                           Tewantin QLD 4565
               [email protected]                                                           07 5329 6500
                                                                                                            Page 1 of 5
Document Set ID: 23688800
Version: 5, Version Date: 16/04/2025
Log in to download the original file

Approved Decision Notice - DBW25 0023 (As Published).pdf · 166 KB (small file)

Full text of the other 4 pages

Page 2

                      Currency Period
               2.     This development approval lapses if the works have not substantially started by 10 April
                      2027, unless an application to extend the currency period is approved by Council.
                      Approved Plans
               3.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the table below.

                        Plan No.             Rev.    Plan/Document Name                          Date

                        Drawing 001                  Site Plan prepared
                                                                 -      by Australian Garages & 1 April 2025
                                                     Sheds
                                                     Annotated by Council

                        Sheet A1                     Building Plans
                                                               -    prepared by Australian 11   February
                                                     Garages & Sheds                       2025

                      External Colours & Finishes
               4.     External colours and finishes must be of muted environmental tones that blend with the
                      surrounding vegetation and landscape, with broad expanses of a single colour or reflective
                      surfaces not permitted.
                      Environment
               5.     Sediment or any other material including building materials or waste products must not be
                      deposited or released into the road reserve, stormwater drain or adjacent properties.
                      Vegetation
               6.     This development permit does not authorise clearing of vegetation, unless otherwise exempt
                      clearing or written authorisation from Council is granted.
                      Stormwater Drainage
               7.     Stormwater runoff from the development must be disposed of on-site without causing scour
                      or damage to the subject site or any adjoining property.
                      Earthworks and Retaining Walls
               8.     All earthworks and associated retaining structures/batters, both above and below ground,
                      both temporary and permanent, must be contained entirely within the subject site unless
                      written permission form the respective landowner(s) is provided to Council. All earthworks
                      must be undertaken in accordance with the provisions of Australian Standard AS3798:
                      Guidelines on Earthworks for Commercial and Residential Developments.
               9.     Any cut or fill of the land within the Biodiversity, Waterways & Wetlands overlay (Riparian
                      Buffer area) required to establish the Shed building pad is to be minimised as much as
                      practicable and generally limited to the envelope of the shed floorplan as shown on the
                      Approved plans. Similarly, any vehicle accessway/ driveway to and from Shed and
                      associated cut or filling of the land is also to be minimised as much as practicable.
               10.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               11.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or


                                                                                                    Page 2 of 5
Document Set ID: 23688800
Version: 5, Version Date: 16/04/2025

Page 3

                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               5.     REFERENCE DOCUMENTS

               Not applicable.
               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      Infrastructure Charges
               1.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
                      Fires in Urban Areas
               2.     In urban areas fires are prohibited except where in an appliance is used for domestic heating
                      or cooking purposes, which must comply with particular standards. Any area identified as a
                      fire pit area on approved plans is to be in accordance with Local Law & Subordinate Local
                      Law No. 3, Schedule 3. Refer to the following link for details:
                      https://www.noosa.qld.gov.au/community/local-laws/local-laws-overview
                      Equitable Access and Facilities
               3.     The plans for the proposed building work have NOT been assessed for compliance with the
                      requirements of the National Construction Code - Building Code of Australia (Volume 1) as
                      they relate to people with disabilities. Your attention is also directed to the fact that in addition
                      to the requirements of the National Construction Code as they relate to people with
                      disabilities, one or more of the following may impact on the proposed building work:
                      a.      the Disability Discrimination Act 1992 (Commonwealth);
                      b.      the Anti-Discrimination Act 1991 (Queensland); and
                      c.      the Disability (Access to Premises – Buildings) Standards
               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required                 Subject of the required Development Permit

                Development Permit for Building Works               All building work

               11.    SUBMISSIONS

               Not applicable.




                                                                                                             Page 3 of 5
Document Set ID: 23688800
Version: 5, Version Date: 16/04/2025

Page 4

               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,




               Andrew Gaffney
               Senior Development Planner


               Enc:   Appeal Rights
                      Approved Plans/Documents




                                                                                                      Page 4 of 5
Document Set ID: 23688800
Version: 5, Version Date: 16/04/2025

Page 5

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 5 of 5
Document Set ID: 23688800
Version: 5, Version Date: 16/04/2025

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.