Approved Decision Notice - DBW25 0023 (As Published)

of 5

Page text shows just the words. Original shows the document exactly as it was published.

                      Currency Period
               2.     This development approval lapses if the works have not substantially started by 10 April
                      2027, unless an application to extend the currency period is approved by Council.
                      Approved Plans
               3.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the table below.

                        Plan No.             Rev.    Plan/Document Name                          Date

                        Drawing 001                  Site Plan prepared
                                                                 -      by Australian Garages & 1 April 2025
                                                     Sheds
                                                     Annotated by Council

                        Sheet A1                     Building Plans
                                                               -    prepared by Australian 11   February
                                                     Garages & Sheds                       2025

                      External Colours & Finishes
               4.     External colours and finishes must be of muted environmental tones that blend with the
                      surrounding vegetation and landscape, with broad expanses of a single colour or reflective
                      surfaces not permitted.
                      Environment
               5.     Sediment or any other material including building materials or waste products must not be
                      deposited or released into the road reserve, stormwater drain or adjacent properties.
                      Vegetation
               6.     This development permit does not authorise clearing of vegetation, unless otherwise exempt
                      clearing or written authorisation from Council is granted.
                      Stormwater Drainage
               7.     Stormwater runoff from the development must be disposed of on-site without causing scour
                      or damage to the subject site or any adjoining property.
                      Earthworks and Retaining Walls
               8.     All earthworks and associated retaining structures/batters, both above and below ground,
                      both temporary and permanent, must be contained entirely within the subject site unless
                      written permission form the respective landowner(s) is provided to Council. All earthworks
                      must be undertaken in accordance with the provisions of Australian Standard AS3798:
                      Guidelines on Earthworks for Commercial and Residential Developments.
               9.     Any cut or fill of the land within the Biodiversity, Waterways & Wetlands overlay (Riparian
                      Buffer area) required to establish the Shed building pad is to be minimised as much as
                      practicable and generally limited to the envelope of the shed floorplan as shown on the
                      Approved plans. Similarly, any vehicle accessway/ driveway to and from Shed and
                      associated cut or filling of the land is also to be minimised as much as practicable.
               10.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               11.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or


                                                                                                    Page 2 of 5
Document Set ID: 23688800
Version: 5, Version Date: 16/04/2025
Log in to download the original file

Approved Decision Notice - DBW25 0023 (As Published).pdf · 166 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.