Original source · versioned page text
Approved Decision Notice - DBW25 0023 (As Published)
Currency Period
2. This development approval lapses if the works have not substantially started by 10 April
2027, unless an application to extend the currency period is approved by Council.
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table below.
Plan No. Rev. Plan/Document Name Date
Drawing 001 Site Plan prepared
- by Australian Garages & 1 April 2025
Sheds
Annotated by Council
Sheet A1 Building Plans
- prepared by Australian 11 February
Garages & Sheds 2025
External Colours & Finishes
4. External colours and finishes must be of muted environmental tones that blend with the
surrounding vegetation and landscape, with broad expanses of a single colour or reflective
surfaces not permitted.
Environment
5. Sediment or any other material including building materials or waste products must not be
deposited or released into the road reserve, stormwater drain or adjacent properties.
Vegetation
6. This development permit does not authorise clearing of vegetation, unless otherwise exempt
clearing or written authorisation from Council is granted.
Stormwater Drainage
7. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site or any adjoining property.
Earthworks and Retaining Walls
8. All earthworks and associated retaining structures/batters, both above and below ground,
both temporary and permanent, must be contained entirely within the subject site unless
written permission form the respective landowner(s) is provided to Council. All earthworks
must be undertaken in accordance with the provisions of Australian Standard AS3798:
Guidelines on Earthworks for Commercial and Residential Developments.
9. Any cut or fill of the land within the Biodiversity, Waterways & Wetlands overlay (Riparian
Buffer area) required to establish the Shed building pad is to be minimised as much as
practicable and generally limited to the envelope of the shed floorplan as shown on the
Approved plans. Similarly, any vehicle accessway/ driveway to and from Shed and
associated cut or filling of the land is also to be minimised as much as practicable.
10. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.
Damage to Services and Assets
11. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
Page 2 of 5
Document Set ID: 23688800
Version: 5, Version Date: 16/04/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original