GENERAL COMMITTEE MEETING 11 DECEMBER 2023
Capital Revenue
Full Year Capital revenue of $10.0 million received comprises cash contributions from
developers ($1.2m) and capital grants ($6.3 million). Note that the timing of capital grant receipts
are generally dependent on the timing of grant conditions and also capital delivery performance,
and that the timing of the receipt of developer contributions (both cash and contributed) is
unpredictable.
Council has funding approval from the Queensland Reconstruction Authority for reconstruction
works relating to the Black Mountain landslip and several other flood impacted sites, which
occurred during the February 2022 rain event. Council has received upfront payments of $24.4
million to fund these works.
Figure 4: Capital Revenue by Type
Capital Program
Actual capital expenditure (excluding commitments) is $24.5 million (YTD budget $20.1 million).
Detailed discussion of progress in the delivery of the capital works program is provided through
a separate quarterly report by the Infrastructure Services Department.
Figure 5: Capital Program Delivery Performance
Page 91 of 126
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.