2016-08-09 Services & Organisation Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 9 AUGUST 2016
BRANCH ACTIVITIES RECENT ACHIEVEMENTS CURRENT PRIORITIES THE NEXT QUARTER
Waste & Environmental Health
Waste
New Waste Contract Drafting of contract documents Providing tours of facilities for Evaluation of tenders is expected to
completed on schedule prospective tenderers. take approximately 2 months and be
The Waste Management tender was Answering questions from tenderers completed early November.
released to the public on Saturday on contract specifications, levels of Report to Council recommending a
2nd July 2016. It is open for 8 weeks service, etc. successful tenderer to December
until August 30. round of meetings
A number of major capital works
projects at the Eumundi Rd facility to
prepare the depot and site for the
next waste contract will commence
in the third quarter 2016.
Waste Reduction and Recycling Plan The Waste Reduction and Recycling Ensuring that the actions contained Ensuring that Council’s WR&R Plan
(WR&R) Plan 2016-24 was adopted in the WR&R Plan are rolled out and is considered when reviewing
by Council in June 2016. followed in the new contract and in contract tenders.
the Towards Zero Waste education
and community engagement
activities.
Commissioning of Cell 2.2. The initial layer of waste to protect Plan the methodology to start cutting Commence cutting in and laying
the liner has now been completed & Cell 2.2. in to Cell 2.1. This will join waste at the interface between cells
the cell is now receiving all types of the waste layers between the 2 cells. 2.2 and 2.1.
waste (except for asbestos).
Laying of an intermediate cap on Cell Negotiated a specification for Obtain the capping specification, Commence works on the
2.1. intermediate capping that the review & approve. Nb It is important intermediate capping.
Contractor will lay at their expense to get the capping completed ASAP
prior to expiration of current contract. due to emerging methane release
problems.
Concrete crushing Awarding the contract for concrete Crushing over 10,000 cubic metres Market the crushed concrete.
crushing. of waste concrete for sale.
Hasting St collection trial Completion of a successful trial to Manage several specific concerns Continue with the 6am start time and
collect bins along Hastings St at held by several businesses around also ensure that recycling is
6am to reduce safety issues and noise. optimized along Hastings Street in
congestion. the new contract.
The 6am start time has remained in
place following the trial & received
support from Hastings St Assoc.
Page 74 of 148
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.