Skip to the record
The definitive source for everything Noosa Council.

Council archive · source document

Delegated Report - Code - Planning OPW26 0105(As Published) · OPW26/0105

of 9

Text shows just the words. Original shows the document exactly as it was published.

                      c.      works programme identifying key components of the works and their respective
                              durations;
                      d.      establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic and services and other relevant issues;
                      e.      include a post out to the local residents and businesses advising of the proposed
                              development, the expected time frames and the site contact details;
                      f.      include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details;
                      g.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager; and
                              ii.      dispute resolution procedures.
                              Any damage to the existing road system as a result of haulage operations shall be fully
                              repaired at the applicant’s expense.
               5.     All necessary approvals from external service providers (e.g., Unitywater) and external
                      parties on which the development works are proposed have been obtained and a copy
                      supplied to Council.
               6.     Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               7.     Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               8.     The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               9.     All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               10.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      the approved plans/documents and conditions detailed in this Decision Notice;
                      b.      the relevant conditions of the higher order Material Change of Use approval viz.
                              132006.413.06 to which this approval relates;
                      c.      all relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines; and
                      d.      the latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                      Pavement Design and Construction
               11.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.

                                                                                                        Page 5 of 9

Document Set ID: 25208649
Version: 2, Version Date: 29/09/2026

Used in these records

About this file

File size
1.9 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning OPW26 0105(As Published).pdf · 1.9 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.