ORDINARY MEETING MINUTES 17 FEBRUARY 2022
96. Cut to fill earthworks must not commence until after the Supervising CPESC has
certified that all installed erosion and sediment controls required by this approval
are sized in accordance with conditions of the approval and the written acceptance
of the certification is provided to the supervising RPEQ by Council officers.
97. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental
Protection Regulation 2019) must not be released from the site or to waters within
the site, or be likely to be released should rainfall occur, unless all reasonable and
practicable measures are taken to prevent or minimise the release and
concentration of contamination.
98. Sediment and erosion control measures must be in place prior to works
commencing. If such measures are not in place or are not satisfactory, “on the
spot” fines may be issued. Such fines can be issued if sediments from the site are
found to enter or have the potential to enter Council’s stormwater system, natural
waterways, any downstream stormwater filtration system or adversely impacting
on other properties. The sediment and erosion control design and measures have
NOT been approved, it is the site's Supervising Engineer who is responsible for
ensuring that the sediment and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance
with "best practise" methods;
b. Been revised by an RPEQ or CPESC to address the issues raised by
changes in the projected construction schedule and/or methods;
c. Been revised to address predicted rainfall events, and
d. Achieve the desired environmental outcomes.
99. Council may request further controls to be installed should the implemented
measures be found inefficient.
100. The erosion and sediment control measures must be designed, installed and
maintained in accordance with the supervising engineer instructions and the
current best practice standards * (Refer to Advisory Note).
101. The developer must ensure non-essential exposure of soil is prevented by
restricting the extent of disturbance and minimising the duration of soil exposure to
adverse weather conditions and effectively turf, cover or stabilise any disturbed
area without delay and prior to rainfall occurring.
102. The developer in conjunction with the engaged CPESC must ensure measures
installed to divert the upstream water are designed and certified by the supervising
RPEQ and installed prior to commencement of bulk earthworks.
103. The developer must ensure sediment does not leave the site or enter onto
adjoining properties or Council’s drainage system due to surface runoff or on tyres
of vehicles and/or machinery. It is essential to implement appropriate approved
erosion and sediment control measures throughout the site during all phases of
construction including vehicle shakedown pad/grid (or similar) at the access to the
construction site. Where sediments or other contaminants are deposited on a road,
they must be removed so as not to enter Council’s drainage system or waterways.
104. Prior to the completion of the development, all site surfaces must be effectively
stabilised. For the purpose of this condition, an effectively stabilised surface is
defined as one that does not, or is not likely to result in visible evidence of soil loss
caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water
contamination.
Page 26 of 33