Erosion and Sediment control checklist and calcs · OPW19/0098

Attached to the e-mail Operational Works application OPW19/0098 - Cover Letter - DA Form 1 - Site Plan - Erosion & Sediment Control checklist - Acid Sulfate Report - Civil Plans - 64 Gateway Drive Noosaville -.

of 5

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

EROSION AND SEDIMENT CONTROL CHECKLIST
The following check list relates to the desired outcomes of Table A of Appendix 2 of the
State Planning Policy

Erosion Control

 Desired Outcome                         Comment
    1. Stage clearing and                As the site earthworks is a balanced cut/fill it is
       construction works to             not possible to stage the works. Notwithstanding
       minimise the area of exposed      the Erosion Risk as per ICEA guidelines is low –
       soil at any time                  refer attached RUSLE calculation
    2. Effectively cover or stabilise    Due to the area involved it is not practical to
       exposed soils prior to            stabilise all exposed areas during the
       predicted rainfall                earthworks activity. Dirty water catch drains are
                                         lined to reduce erosion along concentrated flow
                                         paths
    3. Prior to completion of the        On completion of the bulk earthworks the area
       works for the development.,       will be topsoiled and hydromulched to provide a
       and prior to removal of           grass cove, or covered with mulch depending on
       sediment controls, all            expected duration to future building works
       surfaces must be effectively
       stabilised

Sediment Control

 Desired Outcome                         Comment
    1. Direct runoff from exposed        As noted above the erosion risk for the bulk
       site soils to sediment controls   earthworks activity is low. Notwithstanding the
       that are appropriate to the       lower section of the site will be bunded to
       extent of disturbance and         provide a sediment trap with a rock lined weir
       level of erosion risk             outlet. This is considered in excess of minimum
                                         requirements for a low risk site.
    2. All Exposed areas greater         Clean water diversion drain have been provide
       than 2500m2 must be               to divert external catchments around the
       provided with sediment            disturbed areas. Lined dirty water flow paths
       controls which are designed,      have been provide to direct water to the
       implemented and maintained        sediment trap. The volume of the sediment trap
       to a standard that would          exceeds the size determined using the ICEA
       achieve at least 80% of the       guidelines - refer attached calculations (270m3
       average annual runoff             required, >450m3 provided)
       volume of the contributing
       catchment treated.
Full text of the other 4 pages

Page 2

T jobno: / BSSG
O D ee al =
by: GA

engineers & project managers calculation sheet date 3). 65.18

 

project ©4 GATEWAY DRIVE, MCOSANILLE
subject EROS (OM HAZARD ASSE-SSMEAIT

EROS(OM HAZARD TASK NUMECR
HeiTiAl) SS)

H = HAZARD RATING <TOCO COOK RISK
72OCO  HIaH RISE

T = DURATIOA! OF DISTURBANCE  (monrHS
As AREA OF DISTURBANCE (im)
S= swore FACTOR (TABLE F2 -1ECA Aust.)

K = Soll EROSIVITY FACTOR (RUSLE K FACTOR)

Ts G WEEKS D /. SB MwTHs
A = B7SO Ph ig
S= 0.23 Gore LENGTH BOm, GRADIENT 1-2/)

K = 0.088 D9 ASSUMES Medium PLAST) CIT7 CLAY
NE: SOIL VAT ESTED

H= 1.38 x 8730 *O-23 x 0.058
= IGl < 200

CLASSED AS LOW RISE ,

Noosa: 0754499600 Sunshine Coast: 0753293190 Mackay; 07 4840 2337 PO Box 61, Noosaville, QLD 4566, Australia www.todconsulting.com

Page 3

T jobno: /(8BSSG
OD oe ca = = .
bu: GA

engineers & project managers calculation sheet date 21s g

 

project! GA GATEWAY DRIVE, NIOOSANILLE
subject: RUSLE CALCULATION

TOTAL CATCHMENT = 0.8730 ha
DISTURBED CATCHMENIT = ©. S730 he

ASSUPIEb Soll TEXTURE GROLP = TYPE F

R~ RAINFALL EROSINITY (R- FACTOR)
K = Soil ERODIBILITY FACTOR.

CS = LENGTH GEADIENT FACTOR,

C= COVER MANAGEMENT FACTOR.

P= CROSIOAA CONTTROU PRACTICE FACTOR
A

(f

ANACAL SOIL LOSS FROM EROSION (E/ha/y-)
Az IrRi.jA.| US|). [c | Pp

R= 164.74 (1.1177) 5 Stat

WHERE S = @ TEAR G HR STORM
> IF FoR NOOSAYILLE
= /6.G rete her

K= 6890

K= 0.0S8 — mediurt PLASTICITY CLAY ASSUMED

LS = 0.23 (GLoPe LENGTH 80% cave |-2/-)

c= | (wo cover)
P= (.3 (comPAcTeD AALD SMOOTH fe ConSTRUCTOY
PHASE )

A= GS9Ox 0.0SBx O.7S x! x (-3

=| lz t/ha/ge

ESTIMATES soit CoSS pocS NoT ExXcEED
[so C/ hed ye (ISCA. APPENDIX & PAGE 8.4)

RE COMMERD +

CREATION OF BASIA( USING EXCESS SPOIL ~e
I~ HIGH BLNB TO NORTHERN BooAMEY WITH
WEIR. AT NORTH EAST CORNER . aReST AT IL
4- WS eer. lOn~ UtiBG 4 BOO. pee,

Noosa: 07 54499600 Sunshine Coast: 07 53293190 Mackay: 07 4840 2337 PO Box 61, Noosaville, QLD 4566, Australia. www.todconsulting.com

Page 4

1. Site Data Sheet
                                 Site Name: Gateway Drive

                          Site Location: Noosaville

                                  Precinct: 64 Gateway Drive

                  Description of Site: Preliminary Earthworks


                                                                  Sub-catchments
                  Site area                                                                                    Remarks
                                                 Basin 1
Total catchment area (ha)                        0.873
Disturbed catchment area (ha)                    0.873


Soil analysis (enter sediment type if known, or laboratory particle size data)
Sediment Type (C, F or D) if known:                F
           % sand (fraction 0.02 to 2.00 mm)
            % silt (fraction 0.002 to 0.02 mm)
       % clay (fraction finer than 0.002 mm)
                        Dispersion percentage
                 % of whole soil dispersible
Soil Texture Group                                 F

Rainfall data
Design rainfall depth (days)
Design rainfall depth (percentile)
x-day, y-percentile rainfall event
Rainfall R-factor (if known)
IFD: 2-year, 6-hour storm (if known)              16.6

RUSLE Factors
Rainfall erosivity (R -factor)                    6390     6390     6390   6390    6390   6390   Auto-filled from above
Soil erodibility (K -factor)                      0.058
Slope length (m)                                   80
Slope gradient (%)                                 1.2
Length/gradient (LS -factor)                      0.23
Erosion control practice (P -factor)               1.3
Ground cover (C -factor)                           1

Calculations
Soil loss (t/ha/yr)                               112
Soil Loss Class                                    1
             3
Soil loss (m /ha/yr)                               86

Page 5

4. Volume of Sediment Basins, Type D and Type F Soils
               Basin volume = settling zone volume + sediment storage zone volume

Settling Zone Volume
The settling zone volume for Type F and Type D soils is calculated to provide capacity to contain all
runoff expected from up to the y-percentile rainfall event. The volume of the basin's settling zone (V) can
be determined as a function of the basin's surface area and depth to allow for particles to settle and can
be determined by the following equation:

                                V = 10 x Cv x A x Rx-day, y-%ile (m3)

                         where:

                               10 = a unit conversion factor

                               Cv = the volumetric runoff coefficient defined
                                    as that portion of rainfall that runs off as
                                    stormwater over the x-day period

                     Rx-day, y-%ile = is the x-day total rainfall depth (mm) that
                                      is not exceeded in y percent of rainfall
                                      events. (See Sections 6.3.4(d), (e), (f),
                                      (g) and (h)).

                                  A = total catchment area (ha)

Sediment Storage Zone Volume
In the detailed calculation on Soil Loss Classes 1 to 4 lands, the sediment storage zone can be taken as
50 percent of the settling zone capacity. Alternately designers can design the zone to store the 2-month
soil loss as calculated by the RUSLE (Chapter 6.5.3(d). However, on Soil Loss Classes 5, 6 and 7 lands,
the zone must contain the 2-month soil loss as calculated by the RUSLE (Chapter 6.5.3(d).


Place an "X" in the box below to show the sediment storage zone design parameters used here:
                      50% of settling zone capacity,
               x      2 months soil loss calculated by RUSLE


.                                                                   Average Depth of basin =    0.25    metres

                                            Total    Settling   Sediment    Total            Basin shape
                                         catchment    zone       storage    basin
     Site     Cv        Rx-day, y-%ile
                                            area     volume      volume    volume    L:W       Length      Width
                                            (ha)      (m3)         (m3)      (m3)    Ratio       (m)        (m)

    Basin 1   0.54           54            0.873       255         15       270        3        56.9       19.0
              0.54                                                                     3
              0.54                                                                     3
              0.54                                                                     3
                                                                                       3
                                                                                       3

Used in these records

About this file

File size
1.1 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Erosion and Sediment control checklist and calcs.pdf · 1.1 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.