Cambooya Pty Ltd

Re-compaction of materials should be undertaken under ‘Level 1’ inspection and testing as detailed in
Australian Standard AS3798-2007 Guidelines on Earthworks for Residential and Commercial Developments.
Working platform assessments must be undertaken by a suitably qualified person (i.e., RPEQ geotechnical
engineer) for large plant (e.g., cranes).


6.1.2 Temporary Batter slopes
Temporary unsurcharged batters in loose to very dense sand up to 3 m vertical height should not be formed
steeper than 1V:3H. Flatter batters may be required if localised instability or groundwater is encountered
during construction.


6.1.3 Excavatability
Cut excavations of up to about 3 m high are anticipated. Excavations within this depth range should be
achievable with small to medium earthmoving equipment (i.e., 8 to 12 tonne excavators). Larger machinery
will however improve production rates. Depending on the strength of cementation of the exposed indurated
sand (i.e., coffee rock), ripping attachments may be required.


6.2     Foundations
6.2.1      Site Classification
The site classification derived in accordance with Australian Standard AS 2870-2011 Residential slabs and
footings is not directly applicable to developments of this type but can provide an indication of the likely
magnitude of reactive (shrink and swell) movements associated with normal seasonal soil moisture
variations; and be used for plumbing design.
The site, in its state at the time of our investigation, would be classified as ‘Class ‘S’ in accordance with AS
2870-2011. The estimated characteristic ground surface movement due to seasonal moisture variation (‘ys’
value) is less than 20 mm.
It should be noted that the predicted order of movement is based on the existing soil profile (i.e., no cutting or
filling), and moisture content changes within soils due to normal seasonal moisture variations only (i.e., does
not consider soil settlement).

6.2.2      Footing Design
Conventional high-level strip and pad footings could be considered to support the proposed building.
Footings should found at least 0.4 m into the underlying very dense sand, designed using an allowable
bearing pressure of 400 kPa. Base on the investigation results this will mean footings up to about 1.2 m
depth.
Footing settlements would not be expected to exceed around 1 % of footing width for pads and strips, under
serviceability loads.
A geotechnical engineer must confirm the design bearing pressures during construction. Footing excavations
must be dry and cleaned of any loose, disturbed, or saturated materials prior to pouring concrete.
An alternative to standard footings would be the use of screw pier foundations. This option would reduce the
risk of requiring deeper strip and pad footings if the loose soils are locally deeper in some areas.
If any soil conditions encountered during the footing excavations are found to differ from those noted in the
geotechnical investigation, Core should be notified immediately, and an assessment of the footing
excavations should be carried out to assess if changes to footing design are required.
All footings should found such that they are not adversely affected by any adjacent excavations, batter
slopes, trenches, or retaining walls that are not designed to support building or fill loads.



J001873-001-R-Rev0                                                                                    Page 6

Used in these records

About this file

File size
9.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Appendix E - Geotechnical Report.pdf · 9.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.