To minimise the potential for any adverse interaction effects, footings should found at least below a plane
extending 1 m horizontally from the base of trenches/batter slopes/excavations/retaining walls, then rising up
at 1V:1H. This requirement is illustrated in the following diagram.
6.3 Retaining Wall Design
It is anticipated that the proposed structure walls will retain the excavated soils, therefore, these
structure/retaining walls are considered to be ‘rigid’. Rigid walls are defined as being unable to rotate or tilt,
and should be designed using ‘at-rest’ earth pressure coefficients (K0), as given in Table 1.
Passive pressure (Kp) should be ignored where there is potential for in-ground services trenches (or similar)
in front of the wall.
Table 1: Lateral Earth Pressure Coefficients.
Lateral Earth Pressure
Coefficients
Bulk Friction
Retained Material Density Angle
(kN/m3) (degrees) Kp Ko
Loose sand 17 27 2.66 0.55
Medium dense Sand 18 32 3.26 0.47
Dense sand 19 37 4.02 0.4
Very dense sand 21 42 5.05 0.33
If appropriate, an allowance of 10 kPa should be made for lateral stress induced by compaction plant
operating behind the walls. The effects of surcharge should be included by multiplying the vertical pressure
developed by the surcharge by the appropriate lateral earth pressure coefficient from Table 1.
Drainage material behind the wall should be installed for the full height of the wall, for a width of at least
0.3 m. The material must be free draining and granular and have a perforated or slotted drainage pipe at the
heel of the wall to rapidly remove the water into the stormwater system. Alternatively, the wall will need to be
designed for the full hydrostatic pressure.
6.4 Drainage & Erosion Control
Site drainage should be designed to readily remove surface water and to prevent ponding of water.
Stormwater should be piped to an engineer-designed dissipation system. Concentrated surface water flows
(e.g., roof runoff) should be avoided.
J001873-001-R-Rev0 Page 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix E - Geotechnical Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 9.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.