                      Landscaping Works
               12.    The development site must be landscaped and rehabilitated. The works must be
                      undertaken in accordance with an Operational Works approval and the Noosa Plan for that
                      specific area and must include in particular:
                      a.      A rehabilitation management plan.
                      b.      The land area 10 metres either side of the waterway identified in red on the
                              annotated plan must be rehabilitated and revegetated and removed of all weeds
                              species listed in Planning Scheme Policy 2 Landscaping and Council’s Biosecurity
                              Plan 2020 pest plants listed in Schedule 1 part 3, Schedule 2 and Non-scheduled
                              invasive species.
                      c.      Rehabilitation works must incorporate tree, shrubs, groundcovers, and grasses
                              selected and installed in accordance with the Planning Scheme Policy 2 –
                              Landscaping.
                      d.      The 1 in 2 batters on the northeastern side of the car park must be landscaped with
                              trees shrubs and groundcovers to stabilise and screen the carpark when viewed from
                              Eastern Branch Road.
               13.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
                      Bushfire Management
               14.    The site must be provided with a water storage reservoir having a minimum 5,000 litres of
                      water for emergency firefighting purposes per cabin. Such storage must be provided in
                      addition to the water supply capacity required for the use and must be provided in the form
                      of either an accessible dam, swimming pool, or rainwater tank. If by rainwater tank, water
                      storage for firefighting purposes must be provided either in a separate rainwater tank or a
                      reserve section in the main water supply tank on which:
                      a.      the domestic take off from the tank is at or above the 5,000 litre point; and
                      b.      standard rural fire brigade fittings are fitted to the tank outlet for access by four wheel
                              drive rural services vehicles.
               15.    The site must be provided with an auxiliary power supply such as a petrol driven fire fighter
                      pump (or generator), together with a hose of sufficient length to easily reach around to all
                      sides of the buildings.
               16.    A bushfire evacuation plan for the site must be prepared by a qualified person* and
                      submitted to Council prior to the issue of any Development Permit for Operational Works.
                      *(Refer to Advisory Note)
               17.    A copy of the bushfire evacuation plan for the development must be provided to the nearest
                      fire authority.
               18.    Certification must be submitted to Council from a qualified person* which certifies that the
                      development has been constructed in accordance with the bushfire management
                      conditions of this Decision Notice.
                      *(Refer to Advisory Note)
                      Natural Hazard Management
               19.    The Flood and Fire Management strategies outlined in the Natural Hazard Management
                      Report (doc No. 304-001-01, Rev. A) prepared by BAX Engineering must be adhered to at
                      all times while the use is open for business. In addition to this report, the following must
                      also be prepared, actioned and adhered to at all times while the use is open for business:


                                                                                                         Page 14 of 18

Document Set ID: 22700275
Version: 4, Version Date: 14/12/2023

Used in these records

About this file

File size
5.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning MCU22 0052 [As Published].pdf · 5.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.