Delegated Report - Code - Planning MCU22 0052 [As Published] · MCU22/0052

of 18

Text shows just the words. Original shows the document exactly as it was published.

                      a. Notifying all prospective guests on all advertising devices (i.e., websites, flyers,
                         brochures, etc.) that the site may be inaccessible during rain and fire events;
                      b. A process for management to advise booked guests for the potential for the site to be
                         inaccessible due to predicted weather events; and
                      c. On-site controls and processes for guests currently on-site during flooding and fire
                         events.
                      Water Supply
               20.    The development must be provided with a potable water supply connected to each cabin.
                      The storage capacity of the potable water supply must be a minimum of 5000 litres per
                      guest. The storage capacity of the potable water supply must be a minimum of 4000 litres
                      per guest bedroom/unit/cabin.
                      Wastewater Treatment and Disposal
               21.    The development must be provided with an on-site wastewater treatment and effluent
                      disposal system having a capacity sufficient for the use*.
                      *(Refer to Advisory Note)
                      Site Access and Driveways
               22.    An access driveway must be provided from Eastern Branch Road to all parking and
                      manoeuvring areas of the development. The access driveway must be constructed using
                      an all-purpose weather material. The works must be undertaken in accordance with an
                      Operational Works approval and must be generally in accordance with BAX Engineering’s
                      Roadworks Layout Plan Sheet 2 of 2 (dwg No. 304-001-302, Rev. B).
               23.    The property owner is wholly responsible for the ongoing maintenance of the proposed
                      gravel driveway and gravel walking track. The property owner must ensure that the gravel
                      driveway and gravel walking track are returned to their post-construction conditions after
                      inclement weather events that may have been damaged due to flooding or rainfall.
                      Car Parking
               24.    A minimum of 3 car parking spaces must be provided and marked on the site and made
                      available and accessible at all times while the use is open for business. The works must be
                      undertaken in accordance with an Operational Works approval, be generally in accordance
                      with BAX Engineering’s Overall Roadworks Layout Plan (dwg No. 304-001-300, Rev. B)
                      and must have dimensions, crossfalls and gradients in accordance with Australian
                      Standard AS2890: Parking Facilities.
               25.    All car parking areas and access driveways must be maintained exclusively for vehicle
                      parking and manoeuvring and kept in a tidy and safe condition at all times.
                      Stormwater Drainage
               26.    Stormwater runoff from the development must be disposed of on-site without causing scour
                      or damage to the subject site or any adjoining property.
                      Easements
               27.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               28.    All easements must be designed in accordance with the planning scheme and granted at
                      no cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               29.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.


                                                                                                     Page 15 of 18

Document Set ID: 22700275
Version: 4, Version Date: 14/12/2023

Used in these records

About this file

File size
5.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning MCU22 0052 [As Published].pdf · 5.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.