SPECIAL MEETING AGENDA 7 MARCH 2019
Program Risks Mitigation
There is a potential that the project is Construction through the typically dry season aims to
delayed due to bad weather. mitigate this.
Materials supply, including solar system. Continued communication and frequent meetings with the
contractor to ensure industry suppliers are providing
updates on project timing.
Resource risk Midson Constructions (Qld) Pty Ltd has nominated a
capable team undertaking construction. The appointment
of an external superintendent mitigates the resource risk
for Council.
Construction takes longer than allowed for. The contractor has demonstrated to be well resourced
with an ability to increase crews to reduce risk of delays.
Energex delay the solar connection Midson Constructions (Qld) Pty Ltd will ensure continued
approval. communication with the solar provider and Energex to
maintain the scheduled completion.
Safety Risks Mitigation
Work place health and safety issues Midson Constructions (Qld) Pty Ltd have demonstrated
throughout project, including high risk work extensive experience at working at heights and would be
due to working at heights. appointed as the principal contractor responsible for all
work place health and safety of the site.
Council staff experience excessive noise B&F working group to organise relocations through pre
designated areas and locations.
Scope and Quality Risks Mitigation
Risk of not meeting project objectives. To be managed through Council officer reviews/
milestone meetings, and supported by specialist
consultants who developed the original design and
specifications.
Public Disruption and Council
Mitigation
Reputation Risks
Noise from plant and equipment may be a This will be minimised as much as possible with noisy
cause of disruption to local residents. works completed during business hours.
Solar system does not export to the grid as Energy usage would be at approx. 85% of total capacity
per design. based on a seven day week of power creation.
Consultation
External Consultation - Community & Stakeholder
Liaison with neighbouring properties will be undertaken.
Internal Consultation
Corporate Services was consulted on both the procurement processes and budget.
Infrastructure Services was consulted on the tender scope, submissions and value.
Workplace Health and Safety (Executive Support) was consulted on the evaluation of tender
submissions.
Environment and Sustainable Development was consulted on the tender scope and
evaluation of submissions.
Page 6 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.