2019-03-07 Special Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
SPECIAL MEETING AGENDA 7 MARCH 2019
5. Access and Noise Considerations During Construction
The Tewantin Administration Building will remain operational during the construction phase of the
project, with access restricted to the Level 3 main entrance and other areas at certain times
throughout a working day, due to crane lifts and works being completed above Council staff work
areas.
During construction, excessive noise may be experienced by staff and this may require some areas
to be restricted for extended periods and staff relocated. Buildings and Facilities has established a
working group to plan the scheduled relocations to meet business needs, and the working group
has begun identifying areas and strategies for staff relocation.
The schedule and timing of staff relocations can only be finalised and agreed upon once the tender
has been awarded. The working group will communicate advance notice to staff to mitigate
disruption to business.
Previous Council Consideration
Nil
Finance
Council’s capital program includes funding for the Tewantin Administration Building roof
replacement and solar installation. Council has currently allocated $770,000.00 (excl. GST) in the
current budget, representing a revised budget increase based on the tender submissions and solar
component costs.
Item Cost (excl. GST)
Costs to date (December 2018) $9,969
Tendered Contract Value $771,965
Superintendent Costs $12,000
less Small-scale Technology Certificates (STCs) rebate ($51,808)
Project sub-total $742,126
Potential relocation costs - includes ICT, Accommodation/Lease and Internal $72,040*
Building and Facilities costs
Total Project Cost $814,166.00
*Whilst these costs are not anticipated, based on project team discussions to date with stakeholders/staff
along with the potential for utilising existing Council facilities, they have been included as a ‘worse case’
scenario.
Risks & Opportunities
Finance Risks Mitigation
Council requests for scope increases This is to be mitigated through the Project Control Group
(PCG) and Capital Works Executive (CWE) management
and limitation of client requested scope variations
Contractor claims for variations for Mitigation through PCG and CWE with allowances made
unforeseen issues. within the contingency.
Energex delay the solar connection Continued communication with the solar provider and
approval Energex to maintain the scheduled completion.
Additional costs due to staff relocation Existing Council facility options, staff working from home,
during the project as well as allowing for relocation costs within the project
costs.
Page 5 of 16