         SITE DETAILS                                                                                      GENERAL CONSTRUCTION NOTES                                                                    GENERAL CONSTRUCTION NOTES
         22 Arakoon Crescent, Sunshine Beach,                                                              COPYRIGHT: Drawings remain the Copyright of the Architect: James Russell                      WATER LINES: All hot water lines shall be fully insulated. All domestic hot water to
         Queensland, 4567                                                                                  ALL WORKS shall be carried out in accordance with the most current Building Code of           basins, showers and baths to have maximum temperature of 500C. Allow to supply and
         Lot 793 on RP48111                                                                                Australia,                                                                                    install tempering valves where required, as nominated in the BCA and relevant
         Site Area: 608 sqm                                                                                Australian Standards, Local Council requirements, QDC guidelines and all other                standards.
                                                                                                           relevant by laws and authorities. In particular, refer to current Australian standards
         AREAS                                                                                             even if not referred to below:                                                                STAIR AND BALUSTRADES: All stair and balustrades shall comply with part 3.9 of
                                                                                                           . termite protection BCA and A.S. 3660.1                                                      the BCA. Steps to be provided where fall from dwelling exceeds 190mm.
         PROPOSED                                                                                          . artificial lighting & ventilation BCA parts 3.8.4/3.8.5 and A.S. 1680 . fire safety BCA
                                                                                                           part 3.7                                                                                      PROPRIETARY ITEMS: Identification of a proprietary item does not necessarily imply
         Ground Level                                                                                      . smoke alarms BCA part 3.7.2 and A.S. 3786                                                   exclusive preference for the item so identified, but indicates the necessary properties
         Internal            175                                                                           . glazing BCA part 3.6 and A.S. 1288 and A.S. 2047                                            of the item. If alternatives are proposed, submit proposed alternatives and include
         External            53                                                                                                                                                                          samples, available technical information, reasons for proposed substitutions and cost.
         Sub Total           228                                                                           APPROVAL: No building work shall be undertaken prior to Building Approval by a
                                                                                                           registered Certifier.                                                                          TILES: Expansion joints, walls: 5mm. Floors: 8mm. Fill both with silicone rubber. Grout
         Level 1                                                                                                                                                                                         for wall: Epoxy based mildew resistant. Grout for floors: prepared grout to be acid
         Internal            150                                                                           CONSULTANTS: Drawings shall be read in conjunction with engineers drawings and                resistant. All wall tiles to have FC substrate.
         External            23                                                                            computations. All structure to Engineers design. Hydraulic sizing and design to
         Sub Total           173                                                                           hydraulic engineers requirements if applicable. All drawings to be co-ordinated with          INTERNAL PAINTING: Unless noted otherwise paint system to be Dulux approved 3
                                                                                                           consultant documentation prior to construction.                                               coat system - low sheen finish. Colours to be supplied by Architect during contract and
         Level 2                                                                                                                                                                                         applied as per Dulux's recommendations and guidelines.
         Internal            103                                                                           DIMENSIONS: Do not scale off drawings - use figured dimensions only. Contractor
         External            95                                                                            shall verify all dimensions on site prior to construction. Any discrepancies or errors        POOL: Contractor to confirm heights/depths/steps and plumbing/electrical
         Sub Total           198                                                                           shall be referred to architect and client prior to installation / manufacture of any works.   requirements and locations prior to construction
                                                                                                           Confirm levels & RL's on site prior to commencement of work.
         Internal            428 sqm                                                                                                                                                                     ENERGY EFFICIENCY: all works to be in accordance with BCA Environmental
         External            171 sqm                                                                       SETOUT: Contractor to confirm exact siting and orientation prior to construction setout.       Guidelines and approved energy efficiency report and ESD consultant certificates if
                                                                                                           All building setout and confirmation of setbacks and height to be carried out by a             applicable.
         Site Cover          244.6 sqm                                                                     Licensed Surveyor. No footing, or wall to encroach the title boundary.
                                                                                                                                                                                                         SMOKE ALARMS: To be in accordance with part 3.7.2 of the BCA and AS 3786 to be
         Percentage          40%                                                                           TERMITE PROTECTION: Termite protection by means of termimesh s.s. mesh                        hard wired to consumer supply. Smoke detectors to be of the type with alarms wired
         (all levels)                                                                                      physical barrier in accordance with A.S. 3660.1/2000 and installed in strict accordance       together and having a battery back-up.
                                                                                                           with current manufacturers specifications.
                                                                                                                                                                                                         FIRE ALARM INSTALLATION: Install smoke detection to suite the requirements of AS
                                                                                                           STRUCTURAL STEEL: Unless noted otherwise all exposed structural steel, anchor                 1670.7 and the BCA. Provide any additional detection to areas to allow for compliance
        NOTES                                                                                              bolts and other attachments shall be hot dip galvanised. A cold gal painted finish shall       with AS 1670.1 and the BCA. Builder to provide the electrical contractor's installation
        1. All works to be carried out in accordance with the                                              be applied to any field welding to existing or new steelwork. All steel work cast in           certificate.
        general construction notes on this page of the package                                             concrete footings or slab shall have a bitumen finish applied to full extent of cast in
        2. All works to be carried out in accordance with the                                              concrete steel. Check all dimensions on site prior to fabrication of steelwork.               FIRE SAFETY: Fire safety in accordance with part 3.7 of the BCA.
        DA and BA including drawings & conditions
        3. Handrails are required to all stairways where a change                                          RETAINING WALLS: All retaining walls to structural engineers details. Provide rubble          JOINERY ITEMS SHALL INCLUDE: Manufactured casework items, including:
        of level 575mm or greater occurs as per BCA                                                        backfill and agg drainage to all retaining walls. Builder to provide tanking where             kitchen cabinets and cupboards; bathroom cabinets; robes. Unless noted otherwise:
                                                                                                           required.                                                                                     no exposed gables to joinery; all edges to be square; all joinery units to have carcass
        DEMOLITION                                                                                                                                                                                       constructed of 16mm or 25mm thick pre-finished board; all laminated joinery to have
                                                                                                           SLAB & FOOTINGS: All slabs and footings to structural engineers details. A                    matching abs edging; all timber veneer joinery to have matching solid timber edging;
        1. Demolition or removal of all structures to comply with AS2601.                                  polyethylene moisture barrier shall be lapped 200mm and fully taped under any                 all drawers to have high sides; all adjustable shelves shall be supported on brass
        2. Remove all elements and structures shown hatched or dashed.                                     habitable concrete slab and shall extend 100mm onto the perimeter footing.                    ferrules and bushes - supports to be at 50mm centres; all hinged doors to be hung on
        3. Nominated contractor must carry out their own relevant property                                                                                                                               fully concealed all metal type wide angle hinges; builder to provide adequate noggings
        services searches to confirm location of any essential services.                                    ARTICULATION JOINTS: Provide articulation joints to comply with "Cement and                   to support all bathroom accessories and suspended joinery; finish to underside of
        4. Seek local government or dial-before-you-dig information before                                 Concrete Association Construction Note TN9".                                                  overhead cupboards to match joinery fronts.
        commencing any demolition works on site.
        5. All services (power, gas, water etc) to be disconnected or capped.                              EROSION CONTROLS: All building works to comply with local authorities Erosion and             SANITARY COMPARTMENTS: Provide removable hinges to doors of sanitary
        6. Plumbing drains, stormwater and sewer main to be sealed and                                     sediment control standards.                                                                   compartments to comply with BCA 3.8.3.3 and be readily removable from outside
        capped as required, contractor to obtain plumbing approval from                                                                                                                                  unless there is a clear space of at least 1200mm b/w closet pan within the sanitary
        council as required.                                                                               WATERPROOFING: All wet areas and walls to be waterproofed in accordance with the              compartment and the nearest part of the doorway.
        7. Refer to approved BA for demolition if applicable.                                              BCA 3.8 & AS 3740. Builder to provide certificate of installation and compliance.
                                                                                                                                                                                                         APPLIANCES & EQUIPMENT: Builder to co-ordinate all appliance and equipment
        SETOUT                                                                                             CONCEALMENT OF SERVICES: All services shall be concealed in walls or ducts.                   locations on site and with joiner. Installation and final connection by the contractor.
        1. Builder to organise and provide a copy of the surveyor's pre-build                              Where services are exposed they must be confirmed by the Designer on site prior to             Joiner to confirm all appliance and equipment tolerances and requirements in joinery
        height certificate stating that if the proposal is built as per the approved                        installation unless noted otherwise.                                                          prior to fabrication.
        plans it will not exceed height limits above NGL - as defined by the
        local government (other than the allowable chimney encroachment or                                 LICENSED TRADESPERSONS: All services to be installed by licensed tradespersons                SITE MEASURE: All joinery to be site measured once linings are in place. Confirm
        as outlined in approved siting relaxations - confirm with building                                  in accordance with local authority and with current manufacturers specifications.              any discrepancies prior to fabrication.
        certifier).
        2. Contractor to confirm exact siting and orientation prior to                                      ROOF DRAINAGE: All downpipes to be located as noted on the drawings and sizes.                WEATHERSTRIPS: All external doors to contain weather stripping (type to be
        construction setout.                                                                               Contractor to confirm all roof water collected to be discharged in align with current          confirmed by Architect prior to manufacture).
        3. All building setout and confirmation of setbacks and height to be                                Australian Standards prior to construction.
        carried out by a Licensed Surveyor.                                                                                                                                                              DOCUMENTATION: The contractor shall carry out works in accordance with the
        4. No footing, or wall to encroach the title boundary.                                             SITE DISCHARGE: All stormwater and sanitary plumbing to be connected to existing              signed drawings and schedules and anything reasonable inferred, and with the
        5. Do not scale off drawings, use figured dimensions only- contractor                               council system in accordance with the requirements of the relevant local authority.           Conditions of Contract, and in accordance with the directions and to the satisfaction of
        shall verify all dimensions on site prior to construction.                                                                                                                                       the Architect, whose interpretation of the contract documents shall be final. The
        6. Any discrepancies or errors shall be referred to architect and client                           ALL PRODUCTS: To be installed to manufacturers requirements and to be in                      drawings and specifications/schedules shall be considered complementary, and any
        prior to construction of any works.                                                                accordance with manufacturers requirements for suitable exposure levels.                      work and/or materials absent from one but present or implied in the other shall be
                                                                                                                                                                                                         furnished as if they were present in both.
        SETDOWN
                                                                                                                                                                                                         FINAL CERTIFICATE: At completion of work, Builder to obtain and supply a Certificate
        1. Levels and services locations may vary from those shown - verify                                                                                                                              of Classification from a Building Certifier.
        levels and services locations prior to commencement of construction.
        2. Remove existing landscaping as required by new works unless
        noted otherwise.
        3. Nominated contractor must carry out their own relevant property
        services searches to confirm location of any essential services.
        4. Seek local government or dial-before-you-dig information before
        commencing any demolition works on site.
        5. All services (power, gas, water etc) to be disconnected or capped as
        required.
        6. Plumbing drains, stormwater and sewer main to be sealed and
        capped as required, contractor to obtain plumbing approval from
        council as required.
        7. Termite protection is to be provided to comply with AS3660.1-2000
        and certification is to be provided on completion.
        8. All slabs to be parged.



         PROJECT NUMBER              ADDRESS                                    SCALE   DRAWING NAME    DRAWING NUMBER           DATE                     ISSUE

         1804_arakoon                22 Arakoon Cres, Sunshine Beach            NTS     Lists & Notes   DD 01                    30.04.19                 DA                                                                            JAMES RUSSELL ARCHITECT
GSEducationalVersion

Used in these records

About this file

File size
20.5 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Amended Architectural Plans.pdf · 20.5 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.