Planning Report - 13 Eumundi-Noosa Road, Noosaville QLD 4566 - Dual Occupany
Water Quality and Drainage Code
Table 9.4.8.3—Criteria for assessment
Performance outcomes Acceptable outcomes Response
Stormwater drainage design
PO1 AO1 Complies with AO1
The development and its stormwater A stormwater management plan is prepared
The proposed development will provide a suitable
management system is planned and designed consistent with PSP6 Engineering Design Standards
stormwater management plan in accordance with
having regard to: - Roads, drainage and earthworks.
any relevant standards and guidelines where
1. the natural features of the site; applicable.
2. the need to avoid impacts and potential
risks to ecologically important areas;
3. the likely effectiveness of erosion and
sediment control and stormwater
drainage measures during rainfall events
during and post construction; and
4. the need to protect environmental values
and water quality of receiving waters both
during and post construction.
PO2 AO2.1 Complies with AO2.1
Stormwater drainage infrastructure is planned, Stormwater drainage planning, design and
The proposed development’s stormwater
designed and constructed to: construction is in accordance with PSP6 Engineering
drainage infrastructure will comply with required
Design Standards - Roads, drainage and
standards where applicable.
earthworks and the latest version of the
1. incorporate allowance for increased
Queensland Urban Drainage Design Manual.
flood risk and tidal inundation
through pipework as a result of
AO2.2 Complies with AO2.2
cilmate change and sea level rise;
The stormwater drainage system connects to a
Development Application: 13 Eumundi Noosa Road, Noosaville Noosa Plan 2020: Amendment 1 Effective date: 25/09/2020
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewSearchable page text hides email addresses. Original files are unchanged and may show email addresses.