Planning Report - 13 Eumundi-Noosa Road, Noosaville QLD 4566 - Dual Occupany
Performance outcomes Acceptable outcomes Response
PO10 AO10 Complies with AO10
Excavation and filling for operational works only Filling, other than accessways:
Any filling or excavation undertaken will comply
occur where they:
1. does not extend more than the with appropriate regulations.
1. result in the protection, equivalent of 3 metres around the
rehabilitation and repair main building, measured from the
of ecologically important areas, outer walls of the building;
watercourses, drainage lines and
2. is limited to a maximum of 500m2;
wetlands;
and
2. do not adversely impact on the
3. does not impact on the local
overall hydrology, hydraulics and
drainage of adjoining properties.
flood capacity of a waterway;
3. do not directly, indirectly or
cumulatively cause adverse impacts
external to the site;
4. do not cause increased flooding,
which adversely affects the safety or
use of any land upstream or
downstream;
5. do not cause ponding of water on
the site or nearby land;
6. do not result in a reduction in flood
storage capacity;
7. do not adversely affect the flow of
water in any overland flow path; and
8. do not adversely affect the privacy or
visual amenity of surrounding
property.
Development Application: 13 Eumundi Noosa Road, Noosaville Noosa Plan 2020: Amendment 1 Effective date: 25/09/2020