Plans 2155 01 S A FOR APPROVAL 06 11 2019
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn STORMWATER DRAINAGE
MINIMUM PIT SIZE vs DEPTH GENERAL
Drains:
DEPTH SIZE Provide stormwater drains to connect downpipes, surface drains, subsoil drains and drainage pits to
<600 450x450 the outlet point or point of connection.
600-900 600x600 Downpipe connections:
900-1200 600x900 Turn up drain lines with bends to meet the downpipe, finishing 50 mm (nominal) above finished ground
>1200 900x900 or pavement level. Provide sealed expansion couplings between downpipes and drains.
Pipe Materials:
Stormwater pipe to be F.R.C. or U.P.V.C. class SH in accordance with AS3500.3 Connection to kerb
to be galvanised RHS in accordance with AS1074 with minimum coating mass of 500g/sqr.m
PROVIDE CONCRETE U.N.O. GALVANISED
Identification:
MOWING STRIP TO PEDESTRIAN SAFE LID TO
Lay a detectable strip or plastic tape in the trench after pipelaying, testing and initial backfilling.
INLET PERIMETER SUIT TRAFFIC LOADING PIPE UNDERLAY
General:
Bed piping on a continuous underlay of bedding material, at least 75 mm thick after compaction.
Grade the underlay evenly to the gradient of the pipeline.
Chases:
PIT DEPTH
If necessary, form chases to prevent projections such as sockets and flanges from bearing on the
trench bottom or underlay.
PIPE SURROUNDS
MIN 20mm FALL General:
THROUGH PIT Place the material in the pipe surround in layers 200 mm loose thickness, and compact without
damaging or displacing the piping. Anchor blocks If necessary, provide anchor blocks which restrain
lateral and axial movement of the pipelines at junctions and changes of grade or direction.
ENCASEMENT
General:
PIT SIZE PRECAST CONCRETE OR If necessary, encase the pipeline in concrete at least 150 mm above and below the pipe, and 150 mm
POLYPROPYLENE PIT TO each side or the width of the trench, whichever is the greater. Use Grade N20 concrete to AS 1379.
SUIT TRAFFIC LOADING SUBSOIL DRAINS
TYPICAL S/W PIT General:
Provide subsoil drains to intercept groundwater seepage and prevent water build-up behind walls and
NOT TO SCALE
under floors and pavements. Connect subsoil drains to surface drains or to the stormwater drainage
system as applicable.
Pipe Size & Class:
100mm minimum diameter in accordance with AS2439.1
Pipe depth:
Provide the following minimum clear depths, measured to the crown of the pipe, where the pipe
passes below the following elements:
· 100 mm below formation level of the pavement, kerb or channel.
· 100 mm below the average gradient of the bottom of footings.
· 450 mm below the finished surface of unpaved ground.
Jointing:
At junctions of subsoil pipes provide tees, couplings or adaptors to AS 2439.1.
Trench width:
Minimum 450 mm.
Pipe underlay:
Grade the trench floor evenly to the gradient of the pipeline. If the trench floor is rock, correct any
irregularities with compacted bedding material. Bed piping on a continuous underlay of bedding
material, at least 75 mm thick after compaction. Lay the pipe with one line of perforations at the
bottom.
Chases:
If necessary, form chases to prevent projections such as sockets and flanges from bearing on the
trench bottom or underlay.
Pipe surrounds:
Place the material in the pipe surround in layers 200 mm loose thickness, and compact without
damaging or displacing the piping.
Depth of overlay:
· To the underside of the bases of overlying structures such as pavements, slabs and channels.
· To within 150 mm of the finished surface of unpaved or landscaped areas.
Filter fabric:
Provide polymeric fabric formed from plastic yarn composed of at least 85 by weight propylene,
ethylene, amide or vinyledenechloride, and containing stabilisers or inhibitors which provide resistance
to deterioration due to ultraviolet light.
Marking:
To AS 3705. Protection: Provide heavy duty protective covering. Store clear of the ground and out of
direct sunlight. During installation do not expose the filter fabric to sunlight for more than 14 days.
Filter socks:
Provide polyester permeable socks capable of retaining particles of 0.25 mm size. Securely fit or join
the sock at each joint.
PITS
General:
Finish to exposed surfaces. Co-ordinate finishes with landscape Architect, provide a smooth,
seamless finish, using steel trowelled render or concrete cast in steel forms.
Corners:
Cove or splay internal corners. Metal access covers and grates Standard: To AS 3996.
Cover levels:
Top of cover or grate, including frame:
· In paved areas: Flush with the paving surface.
· In landscaped areas: 25 mm above finished surface.
CONTOUR
PLAN DETAILS: PLAN AMENDMENTS: PLAN TITLE:
Designed: JT
Rev Date Comment Altered Checked DRIVEWAY AND CARPORT RECTIFICATION
HYDRAULIC NOTES
Drawn:
Checked:
JT
BR
A 05/11/19 ISSUE FOR APPROVAL JT BR
83 NOOSA PARADE, NOOSA HEADS
A.B.N. 62 117 061 659
PO Box 474, Buddina 4575, Qld
6 Innovation Parkway, Kawana Waters 4575, Qld
Datum:
Date:
AHD
NOV 2019 ADVISORY SERVICES QLD FOR APPROVAL
Ph. (07) 5493 9777 Fax (07) 5493 6888 This plan is Copyright. Other than for the purposes of and subject to the conditions prescribed under the Copyright Act, no part of it may in any form or by
Website: www.ContourCE.com.au Quality Assured
International 3rd Party Accredited
any means be reproduced, stored in a retrieval system or transmitted without the prior written permission of Contour Consulting Engineers. The plan shall not
be used for construction without prior written approval.
PLAN No: 2155 01 S 111 REVISION: A
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.