THE NOOSA ECONOMY
No. Project Responsibility Update Status
1. Commence renewal of Park Road boardwalk Infrastructure Planning, Design & Delivery Tenders have closed and are being evaluated. On track @
Manager
2 ‘Finalise construction of Rufous Street Digital Hub project (Stage Economic Development Manager Construction of the Digital Hub building and restoration of the surrounding On track @
1) and adoption of hub operating model parkland will be completed by Easter. Commenced process to appoint a
Coordinator for the Digital Hub.
3 Continued implementation of Local Economic Plan_ incl. Economic Development Manager Continued to deliver on Local Economic Plan Priority actions, highlights On track g
providing support to existing industry representative groups and include the launch of the Economic Grants Program and strong industry
evaluation of peak body models engagement in relation to the development of the New Planning Scheme.
LONG TERM PLANNING FOR NOOSA SHIRE
No. Project Responsibility Update Status
1 Finalise drafting of new Noosa Planning Scheme and obtain Planning Scheme Project Manager Council resolved to prepare the Scheme under the Planning Act on 16 On track Q
Queensland Government approval November 2017. Bulk of the drafting has been completed with a few final
issues being workshopped with Councillors. Zoning maps, overlay maps
and higher order Strategic Framework maps all being finalised. Urban
design consultancy work nearing completion. Draft Retail Needs Analysis
received to help with centres. Intention to present a draft scheme to
Council before end March 2018.
2 Develop Climate Change Adaptation Plan & actions (Stage 1) Project Coordinator - Climate Change Coastal hazards adaptation plan project on schedule. Risk mitigation On track @
Adaptation options analysis being paused to allow appropriate time for stakeholder
engagement. This will have no effect on the final delivery date of the plan
in late 2018.
3 Finalise Noosa River foreshore management plan and Property Manager Draft Master plan going out to public consultation 22 January 2018 On track Q
commence implementation
4 Complete detailed asset management plans for identified pilot Asset Planning Manager Asset management plan template has been agreed on. NAC & Slurry On track 8
areas and commence development of asset management plans Systems AMP's to be presented to March round of Council meetings.
for the remaining infrastructure classes Roads & Bridges AMP's drafted but will not be completed until the
conclusion of the revaluation period to factor in adjusted unit rates and
depreciation.
5 Commence implementation of priority actions from Council's Director Infrastructure Services Project Manager interviews have been undertaken. Transport audit in On track g
Transport Strategy Hastings Street precinct will be conducted on 3 January 2018. Christmas
Free Holiday Buses completed. Schools program to commence in Term 1.
6 Commence detailed design of North Shore Beachfront Property Manager The detailed design has commenced and construction is due to Behind Schedule @
campground redevelopment including environmental restoration commence May/June 2018.
works
7 Review of Noosa Community Support operating model in Community Facilities Manager Discussions with the Federal and State Funding agencies regarding the On track @
preparation for new funding arrangements operations of Noosa Community Support scheduled for the third quarter
of 2017/18.
8 Development of a robust 10-year Capital Works Program Asset Planning Manager Intent is for the 10 year capital program to be prepared by the end of the Behind Schedule O
financial year.
Page 35 of 144See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.