SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 6 FEBRUARY 2018
BRANCH ACTIVITIES RECENT ACHIEVEMENTS CURRENT PRIORITIES THE NEXT QUARTER
Capital Works Program A draft 5 year program is being Initial workshops have commenced Have a draft 5 year capital program
- The development from a 5yr capital prepared for future budget in establishing a capital works prepared for the April 2017 budget
works program to a 10 year capital workshops. program for 2018/2019. workshop.
works program that is aligned to
Councils long term financial planning.
Business as Usual activities Completion of customer requests Ensure customer enquiries are Further develop systems and
continue to be undertaken by staff. being addressed in a timely manner. processes to better respond to
technical enquiries relating to
technical issues.
Buildings & Facilities
Align to Council’s mobility system and Continued use and training being Further training & development to be Ongoing development and use of
roll out undertaken. established for new electrician. mobility system that are aligned to
Continued development of cyclic Council’s asset management
activities into the work management systems.
system.
Compliance auditing of shire wide assets 50% of the Council owned buildings Documentation loaded to ECM Continue priority inspections.
to ensure legislative requirements are have been audited. Continued compliance checks.
being met
Create a critical asset register to align to Outlined register and commence Continued asset capture and Finalise asset register and confirm
asset management objectives population of assets populate register. accuracy.
Undertake condition assessments of Scheduled amenities condition Complete condition assessments Finalise condition assessments.
public amenities assessment with external support. Collating data. Finalise collected data into asset
management system.
Delivery of 90% of Capital Works Reviewed capital works program Continued monitoring of project Ensure projects meeting milestones.
Program as approved by CWE Continue to track and ensure capital milestones and financial tracking. Financial projections are on target.
works completion. Tender preparation for financial Close out completed projects.
New capital works projects identified approval.
and tracking.
Business as Usual activities Trade Services Panel approved Review preventative maintenance Implement identified preventative
Unity water MOU installation of tasks & contracts continued for maintenance changes.
bottle filling stations newly identified equipment. Advise successful tenderers.
Installed dog wash facility at Beach 2018/19 Budget build from base. Review of electrical services across
Access 47, Marcus Beach. Continued review of services. the shire.
Electrician position filled. Working through Council owned Continued monitoring of portfolio.
Electrical services being assessed facilities asset capture. Continued assistance provided to
and moved in house where possible. the wider business group and shire.
Page 65 of 144
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.