Minor Change Existing Approval - MCU17 0568 02 & OPW17 0602 02 (As Published)

of 15

Page text shows just the words. Original shows the document exactly as it was published.

               35.    A Construction Management Plan must be submitted to Council for approval prior to the
                      prestart meeting and must specifically include/address the following:
                      a)      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures to be installed prior to construction.
                              ii.      Fencing to the work site during the construction phase to ensure the safety of the
                                       public and the road users.
                              iii.     Maintenance of safe pedestrians and cyclists access across the frontage of the
                                       site both during daily construction and after daily construction has ceased.
                              iv.      Sufficient parking arrangements for trucks, machineries and construction workers
                                       without adversely impacting on traffic flow and/or the availability of on-street
                                       parking in the local street.
                      b)      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures.
                      c)      Works programme identifying key components of the works and their respective
                              durations.
                      d)      The proposed dates for the commencement and the completion of the works.
                      e)      Effective procedures and measures to minimise adverse environmental impact on
                              other properties and roads users including noise and dust emission.

                      f)      Establishment of a communication protocol with the adjoining owners and any other
                              affected parties to advise of construction times, impacts on traffic and services and any
                              other relevant issues.
                      g)      Identification of communication and complaint management procedures including:
                              i.       Contact details for the on-site manager.
                              ii.      Dispute resolution procedures.
               36.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               37.    Any alteration to existing services or conflict between the development and an existing or
                      proposed service must be referred to the relevant service authority for determination prior to
                      commencement of works.
               DURING CONSTRUCTION
                      General
               38.    The developer must meet any costs to repair damage to any Council’s and/or public asset
                      during construction, where damage is a result of the development works. Damage to assets
                      must be repaired immediately where it creates a hazard to the community. In circumstances
                      where the damage does not create a hazard to the community, it must be repaired
                      immediately on completion of the works associated with the development.
               39.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works (eg public pathway)
                      are involved, such confirmation must be submitted for the respective hold points prior to any
                      site inspection by Council Officers.




                                                                                                           Page 6 of 15
Document Set ID: 25022269
Version: 4, Version Date: 30/07/2026
Log in to download the original file

Minor Change Existing Approval - MCU17 0568 02 & OPW17 0602 02 (As Published).pdf · 195 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.