Minor Change Existing Approval 131998 981643 3 [As Published]
33 Prior to the commencement of development, the following Development Permits must be
obtained: -
33.1 Development Permit for building works.
Additional Condition – 14 March 2025 – 131998.981643.3
Approved Plans
34. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the tables below.
Plan No. Rev. Plan/Document Name Date
131998.981643.3 – Internal conversion of floor area – Tenancy A1
222 DA Plan – -Proposed Ground prepared by 3 September
Onesto Group 2024
5. REFERRAL AGENCIES
Not applicable
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
1. Approval of this development application will trigger an Infrastructure Charge in accordance
with the Coastal Major Road Network Infrastructure Charges Plan for the estimated amount
of $17,283. This amount will subject to variations in the Consumer Price Index, All Groups
Brisbane from September 2004 until the date of payment. An Infrastructure Charge Notice
will be issued in accordance with Chapter 5 of the Integrated Planning Act 1997.
Payment via credit card transaction will not be an acceptable method of payment for
development contributions conditioned in this permit or for infrastructure charge notices
issued separately.
2 We advise ‘interested parties’ i.e. ‘developer’, ‘owner’, ‘tenant’ to consider their
responsibilities under the Disability Discrimination Act (DDA) in regard to the installation of
disabled access and the provision of disabled facilities, and that access to this building and
the provision of sanitary facilities may need to comply with the requirements of Section D
Part D3 and Section F Clause F2.4 of the Building Code of Australia.
3 Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act
if the cost of operational works exceeds $80,000, then a portable long service levy is required
to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight the
approved form issued by the Building and Construction Industry (Portable Long Service
Leave) Authority that confirms that the requirements of the Act have been satisfied. A
statutory declaration outlining the cost of the operational works must be submitted to Council
with the lodgement of any application for operational works over the site
Infrastructure Charges
4. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
7. PROPERTY NOTES
Not applicable
Page 5 of 7
Document Set ID: 23644212
Version: 2, Version Date: 20/03/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original