NOOSA AQUATICS CENTRE UPGRADE PLAN AND NOOSA AQUATICS FACILITIES STRATEGIC PLAN · Attachment 1 NAC Upgrade Plan
NOOSA AQUATIC CENTRE
PRIORITISED IMPLEMENTATION PLAN sheet 4 of 7
6 Girraween Ct, Sunshine Beach
The following prioritised implementation plan outlines each improvement element in chronological order, scheduled over a 1–20 year project life cycle. Staging the
implementation of the plan will allow expenditure to be distributed across multiple budget years, enhance opportunities to access external funding and facilitate the
amortisation of costs over a longer period. The staging will also ensure minimised disruption to facilities for users.
The inclusion of elements in the upgrade plan does not represent a commitment from Council to fund proposed improvements, works or upgrades. Plan elements
identified in the implementation plan are indications of future improvements or enhancements and are not a guarantee of implementation. The implementation of
construction projects recommended in this plan is subject to relevant approvals.
50m Pool
Upgrade plan element Detail Feedback/rationale Hub
Priority upgrades
25m Pool
Hub
Critical filtration system upgrades Provision of new pool filtration systems for 50m and 25m pools in space where current Internal Council feedback confirms that the current pump system
south western carport area is located. (Including option for pool cooling.) requires replacement to comply with WHS and required quality of
Wellness
filtration. Hub
Plans and approvals Engagement of architectural and engineering consultants to provide design development Commissioning of architectural and engineering consultants to provide LTS and
and BA drawings and approvals for new and refit building works. design development and BA drawings for approvals of new and/or refit Play Hub
building works. Changeroom, Creche,
Gym and Multi-Purpose
New western 25m Pool Hub Construction of new compliant amenities building for western side of facility at 25m pool A minor western amenities block will provide convenient toilets/change Room Building
amenities building and lifeguard level, and new lifeguard office with observation decks viewing both 25m and 50m pools rooms for the western pool area and wellness hub courtyard, and also
Administration and Cafe
office above at 50m pool level comprising: provide an interim facility when the main amenities block is rebuilt. Building
25m Pool Level:
- PWD ensuite change room (x1) Common Areas
- Ambulant shower cubicles with extended length and change bench (x3)
- Ambulant toilet cubicles with extended length and change bench (x2)
- Outdoor showers (x2) Plans and Approvals
- Necessary retaining wall works
- Upgrades to adjacent existing stairs to ensure BCA compliance
50m Pool Level:
- Lifeguard office space
- Observation decks to both 25m and 50m pools
- Necessary balustrading to ensure user safety
- Stair and ramp access from 50m pool level
- New solar panels to roof
New pool hoist Replacement of existing pool hoist with one or more contemporary, compliant pool All abilities use.
hoists.
Interim existing changeroom Interim retrofit of existing changeroom building to cater for users with disabilities and
building upgrades families. Installation of additional outdoor showers.
Priority existing car park upgrades Increase PWD parking spaces and tidy, re-mulch and interplant entry gardens as interim Management has identified maintenance upgrade needed.
upgrade.
Bike storage (stage 1) Provision of stage 1 of secure bike storage at entry (e.g. bikeep). Secure bike storage will encourage active transport.
New entry signage Construction of new entry signage in car park and building entry, including associated Improve inclusion/accessibility/legibility/wayfinding.
landscaping works.
Spectator shelters Replacement of existing and provision of new spectator shelters (x3) with aluminium Most existing shade structures are nearing end of life, additional shade is
bench seating under after designs and approvals are completed to ensure cohesive needed throughout site.
design. Style, materials and colour palette to reflect new building designs and palettes.
Secondary entry Formalisation of designated entry for schools and other large groups from eastern car A secondary entry off the eastern car park will alleviate pressure from the
park including: main entry when schools and other groups visit the facility.
- New entry gates with swipe card entry
- Associated footpaths
- Associated wayfinding signage
Programmed water/splash park Upgrade of existing toddler pool area with new splash park elements, consider nature- Stakeholder feedback has resulted in requests to update the existing
elements themed water play with in-situ boulders and stream like systems with sluice gates and water play features in bubble/toddler pool. Existing features are
manually activated water misters and pistols. nearing end of life.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Attachment 1 NAC Upgrade Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.