PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 10 SEPTEMBER 2019
REPORTS FOR CONSIDERATION OF THE COMMITTEE
1 UPDATE TO INFRASTRUCTURE CHARGES RESOLUTION
DOCUMENT INFORM AT ION
Author Infrastructure Assessment Coordinator, Oddbjorn Ludvigsen
Environment and Sustainable Development Department
Index ECM/ Subject/ 66.02 - Infrastructure Charges Instruments & Policy
(Council/State)
Attachments 1. Noosa Shire Council Charges Resolution (No.4) 2019
(30 page attachment provided separately to this agenda)
EXECUTIVE SUMMARY
Not applicable
RECOMMENDATION
That Council note the report by the Infrastructure Assessment Coordinator to the Planning &
Environment Committee Meeting dated 10 September 2019 and adopt the “Noosa Shire Council
Charges Resolution (No.4) 2019” provided at Attachment 1 to the report, to take effect on
Monday 23 September 2019 replacing the “Noosa Shire Council Charges Resolution (No.3)
2018”.
REPORT
Council issues infrastructure charges on development under its “Charges Resolution” to help
fund provision of “trunk” infrastructure identified in its Local Government Infrastructure Plan
(LGIP).
Legislative amendments to infrastructure charges requirements regularly occur and it is therefore
appropriate that Council also regularly review and update its “Charges Resolution” accordingly to
ensure continued best compliance with the current Planning Act 2016 and Planning Regulation
2017.
A review of Council’s current “Charges Resolution” has been triggered by the following recent
events:
a) Amendment of the Planning Regulation 2017 where the prescribed amounts (i.e. maximum
infrastructure charge rates) have been updated to the current 2019-2020 financial year.
The maximum prescribed amounts have increased by approximately 2.25% on average.
b) Unitywater having adopted its own Infrastructure Charges Schedule to better comply with
its respective legislation, the “South-East Queensland Water (Distribution and Retail
Restructuring) Act 2009” (SEQ Water Act). This has resulted in some aspects of Council’s
“Charges Resolution” becoming redundant and no longer applicable. The only item that
continues to bind Council and Unitywater is the actual “Break-up Agreement” in Section
10.2 and Table 10.1.
c) Recent Court Judgements on infrastructure charges appeals have highlighted the
importance of clarity in resolution details in issuing charges, particularly on non-specific
types of development.
Staff have reviewed Council’s current “Charges Resolution (No.3) 2018” and recommend it be
updated and replaced with the amended “Charges Resolution (No.4) 2019” provided as
Attachment 1 to this report. The amended sections are highlighted in yellow shading for
reference and are summarised below:
Page 3 of 76
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.