App C - Current Decision Notice and Approved Plans

of 35
                      *(Refer to Advisory Note)
               42.    Where damage occurs to any Council asset as a result of the development works, it must be
                      repaired immediately where it creates a hazard that presents risk to person or property. Other
                      damage must be repaired prior to completion of works.
               43.    Street trees must:
                      a.      Meet AS2303 Tree stock for landscape use.
                      b.      Be located in accordance with engineering requirements for safe vehicle and
                              pedestrian sight lines.
               44.    The finished level of all mulch in garden beds and landscaped medians is to be a minimum
                      of 50mm below the level of the adjacent top of kerb. All landscaping is to be constructed in
                      accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
               45.    Suitable root barriers must be installed where proposed trees are adjacent to paths,
                      pavement etc in accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
               46.    An inspection is to be carried out with the relevant Council officers, the Contractor and
                      Supervising Engineer after road centrelines have been established, and prior to clearing
                      being carried out. This inspection is to deal with the limits of clearing to be carried out for this
                      development. This meeting is to take place prior to the “Pre-start” meeting.
               Damage to Services and Assets
               47.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
               Any repair work which proposes to alter the alignment or level of existing services and assets must
               first be referred to the relevant service authority for approval.
               FOLLOWING CONSTRUCTION / PRIOR TO THE COMMENCEMENT OF THE USE / COUNCIL
               SIGNING THE PLAN OF SURVEY
                      Certification
               48.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.
                      Supervision/Certification
               49.    Prior to commencement of use the following (prepared by respective qualified persons* and
                      certifying compliance with approvals) must be submitted to Council:
                      a.      Landscaping certification confirming all works have been constructed in accordance
                              with conditions of approval.
                      *(Refer to Advisory Note)




                                                                                                          Page 13 of 18
Document Set ID: 24223542
Version: 4, Version Date: 15/10/2025

Log in to download the original (App C - Current Decision Notice and Approved Plans.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.