Evaluation of Gully Pit Inlet Litter Control Systems– Brisbane City Council and Gold Coast City Council
all litter had passed through the chamber except for an aluminium
can.
Hydraulic performance.
On-grade:
The mesh insert did not significantly effect the hydraulic capture
performance of the gully pit for all longitudinal slopes.
Sag:
At 0% (sag) longitudinal slope, the mesh insert caused the inlet to reach
‘orifice’ condition sooner (ie. at a smaller approach flow).
200
180
160
140
120
Depth at Invert (mm)
100
80
60
meshed pit
40
standard pit
20
0
0 50 100 150 200 250 300 350 400 450 500
Approach Flow (L/s)
Figure 4: Sag “0” Grate results – meshed pit insert
Discussion:
From the observations above, the ‘blocked’ meshed insert had no
significant effect on the hydraulic capture performance (on-grade) of the
inlet. All floatable litter passed through the chamber at 25L/sec and
semi-buoyant litter was remobilised at flows greater than 25L/sec.
For the sag condition, the insert affected the hydraulic capture between
150-340L/sec. Above 340L/sec it would appear that the capture (orifice)
was controlled by the inlet opening.
Urban Water Resources Centre 11 University of South Australia
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.