Gross Pollutant and Suspended Solids Removal
All of the site’s impervious areas discharge to suitable treatment device/s
Treatment device selection criteria are to be in accordance with Industry Best Practice and,
WSUD Engineering Guidelines
Provide engineering diagrams of the stormwater quality treatment of the proposed development
6.2 Site Analysis and Design Strategy
6.2.1 Pre-Development Phase
An Erosion Hazard Assessment has been carried out for the proposed development – refer to
Appendix E for a copy of the completed Noosa Shire Council form. As a result of this assessment,
it was determined that the overall site is a ‘low’ risk.
Prior to construction commencing, the following erosion and sediment control measures will need to
be installed around the subject site to minimise disturbance and ensure the quality of runoff
discharging from the site is of an acceptable standard:
Sediment barriers to be installed on all entrances to downstream stormwater infrastructure (i.e.
gully pits);
Designation of transport routes through the site to minimise vegetation disturbance;
Maximise retention of existing vegetation to reduce soil disturbance and provide filter strip
treatment for runoff;
Install construction entry and exit shakedown areas;
Sediment fences are to be installed on the downstream boundaries of the subject site; and
Install dust control measures as required.
All erosion and sediment control measures are to be designed and installed in accordance with IECA
Guidelines. Further details regarding the proposed erosion and sediment control measures will be
provided during the detailed design phase of the development.
Further to the above considerations, it is the developments intent to limit ground disturbing activities
to a minimum. Other than the final carparking area, all structures and footpaths are proposed to be
suspended over the natural surface.
6.2.2 Bulk Earthworks Phase
During the bulk earthworks phase, the following erosion and sediment control measure will need to
be installed in addition to the aforementioned measures (Pre-Development Phase) to ensure there
is minimal disturbance to downstream receiving water bodies:
Construction chutes to control runoff over earthworks batters;
Construction of temporary bunds at the top of all earthworks batters to ensure runoff is directed
away from exposed batters;
Sediment basins to be constructed at low points within each stage of the proposed development;
Sediment fences to be installed on the downstream side of any stockpiles; and
BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH Page 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8 - Site Based Stormwater Managment Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 34.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.