Attachment 8 - Site Based Stormwater Managment Plan · MCU22/0118

of 81

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (34.8 MB): may take a few minutes to open.

Log in to see the plans as drawn
                                                                RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                                       22366 C R10 R003 (04.07.22)

                                                                                                         July 2022


6        STORMWATER QUALITY ASSESSMENT
6.1      Treatment Objectives
         This assessment identifies issues relating to stormwater quality runoff and assesses possible
         methods of treatment if required. The aim of this section of the report is to determine practical
         approaches to achieving improvements in the quality of the stormwater run-off from the site that can
         be readily implemented.

         The SPP 2017 proposes criteria which apply to ‘high-risk’ development for stormwater. The criteria
         include one or more of the following:

            A Material Change of Use (MCU) for an urban purpose which involves greater than 2,500m2 of
            land that:

            will result in an impervious area greater than 25% of the net developable area; or

            will result in six (6) or more dwellings

            A Reconfiguration of a Lot (ROL) for urban purposes that involves a land area greater than
            2,500m2 and will result in six (6) or more lots; or

            Operational works for urban purposes that involve disturbing more than 2,500m2 of land.

         The proposal includes an MCU for a land area of 2,500m 2 that will result in impervious area greater
         than 25% of the developable area. Hence, the development is classed as ‘high risk’ for water quality
         and the SPP 2017 applies.

         The SPP 2017 suggests the development aims to:

            Avoid or otherwise minimises adverse impacts on the environmental values of receiving waters,
            arising from:

            altered stormwater quality or flows, and

            wastewater (other than contaminated stormwater and sewage), and

            the creation or expansion of non-tidal artificial waterways, and

            Demonstrate compliance with the SPP code - Water quality (Appendix 3).

         Appendix 2 (Table B) of SPP 2017 suggests ‘Post Construction Phase – Stormwater Management
         Design Objectives’ as:

                                    Table 2 - South East Queensland (SEQ) Targets

          Total Suspended Solids         Total Phosphorus        Total Nitrogen           Gross Pollutants
                   (TSS)                        (TP)                  (TN)                    >5mm

                80% Removal                60% Removal            45% Removal               90% Removal


         The objective is to provide the following:

            Nitrogen and Phosphorous removal


BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH                              Page 11

Used in these records

About this file

File size
34.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 8 - Site Based Stormwater Managment Plan.pdf · 34.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗