6 STORMWATER QUALITY ASSESSMENT
6.1 Treatment Objectives
This assessment identifies issues relating to stormwater quality runoff and assesses possible
methods of treatment if required. The aim of this section of the report is to determine practical
approaches to achieving improvements in the quality of the stormwater run-off from the site that can
be readily implemented.
The SPP 2017 proposes criteria which apply to ‘high-risk’ development for stormwater. The criteria
include one or more of the following:
A Material Change of Use (MCU) for an urban purpose which involves greater than 2,500m2 of
land that:
will result in an impervious area greater than 25% of the net developable area; or
will result in six (6) or more dwellings
A Reconfiguration of a Lot (ROL) for urban purposes that involves a land area greater than
2,500m2 and will result in six (6) or more lots; or
Operational works for urban purposes that involve disturbing more than 2,500m2 of land.
The proposal includes an MCU for a land area of 2,500m 2 that will result in impervious area greater
than 25% of the developable area. Hence, the development is classed as ‘high risk’ for water quality
and the SPP 2017 applies.
The SPP 2017 suggests the development aims to:
Avoid or otherwise minimises adverse impacts on the environmental values of receiving waters,
arising from:
altered stormwater quality or flows, and
wastewater (other than contaminated stormwater and sewage), and
the creation or expansion of non-tidal artificial waterways, and
Demonstrate compliance with the SPP code - Water quality (Appendix 3).
Appendix 2 (Table B) of SPP 2017 suggests ‘Post Construction Phase – Stormwater Management
Design Objectives’ as:
Table 2 - South East Queensland (SEQ) Targets
Total Suspended Solids Total Phosphorus Total Nitrogen Gross Pollutants
(TSS) (TP) (TN) >5mm
80% Removal 60% Removal 45% Removal 90% Removal
The objective is to provide the following:
Nitrogen and Phosphorous removal
BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH Page 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8 - Site Based Stormwater Managment Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 34.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.