RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads
22366 C R10 R003 (04.07.22)
July 2022
responsibility of the owners of the development. The maintenance should be carried out in
accordance with the Council and Noosa RACV Resort recommendations.
6.4.1 First Flush Device
First flush device/s to divert initial flows (first 12mm of rainfall or hose-down) to the vegetated
area.
The initial runoff from the site’s roof area will be directed to the non-disturbed vegetated areas via a
first flush device/s. This will ensure that accumulated loose material collected in the initial roof runoff
during a rainfall event is collected and diverted to landscape/garden areas before flows enter the
rainwater and tank. A first flush device has a set limit on its capacity to convey flows. Once the initial
runoff from a rainfall event meets this capacity of the first flush device, the remainder of flows for the
event are diverted to the Lawful Point of Discharge.
6.4.2 Bioretention Basin
A minimum 30m2 surface area bioretention basin.
Bioretention basins remove contaminants and sedimentation from stormwater runoff via infiltration
through layers of soil media. The basin is made of a 400mm filter media layer and a 100mm transition
layer located above in-situ soil. The basin is to be vegetated, as per the landscape architect’s
recommendations. These plants provide additional treatment and will prevent clogging of the basin.
Runoff within the bioretention area gradually infiltrates the soil layers, and freely discharge subsoil to
an outfall to Weyba Creek. This will be confirmed in the detailed design stage.
6.5 Rainwater Harvesting – Reuse Minimum Sizing of Rainwater Tank
To satisfy Council’s code performance outcomes by reducing the need for mains water, the roof area
is to be connected to a rainwater tank with a minimum capacity of 5,000L in accordance with
Department of Housing and Public Works MP4.2 – Rainwater Tanks and Other Supplementary Water
Supply Systems. This equates to a total rainwater tank volume of 40 kL. Each rainwater tank is to be
plumbed to be available for outdoor cleaning, washing machines and toilet flushing in accordance
with Council’s WSUD Planning Scheme Policies.
6.5.1 Internal Demand
To calculate expected internal demand, the following assumptions were made:
Toilet requires 25 L/day (per person) in accordance with Table 4.4 of the MUSIC Modelling
Guidelines 2010;
Laundry requires 21 L/day (per person) in accordance with Table 4.4 of the MUSIC Modelling
Guidelines 2010;
Peak occupancy of two (2) people per dwelling for the proposed 16x 2-bedroom units for the
holiday accommodation in accordance with Table 4.3 of the MUSIC Modelling Guidelines 2010.
Based on these assumptions the required volume for the internal demand component of the
rainwater tank is calculated as;
25 L/day (per person) + 21 L/day (per person) x 2 people per dwelling (peak) = 92 L/day
Daily demand (representing indoor use) = 92 L/d / 16 units = 1,472 L / day = 1.472 kL / day
BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH Page 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8 - Site Based Stormwater Managment Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 34.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.