Negotiated Report (Representations made) MCU24 0125, OPW24 0150 & RAL24 0021 (As Published) · MCU24/0125

of 39

Text shows just the words. Original shows the document exactly as it was published.

                        ED 24175 OPW-           C       Planting Plan prepared by Element Design      06/05/25
                        11

                        Amendments                  •   Update Plant schedule

               CURRENCY PERIOD
               3.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 6 September 2027, unless an application to extend the currency
                      period is approved by Council.
               SITE SPECIFIC CONDITIONS
                      Bonds
               4.     A site control and/or compliance bond of $20,000 is to be submitted to Council prior to the
                      pre-start meeting. The pre-start meeting will only be held once Council's Construction
                      Engineering Officer has confirmation that the bond monies have been received by Council.
                      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
               5.     Bonds must:
                      a.      meet the requirements of Council’s relevant Planning Scheme Policy for performance
                              and uncompleted works;
                      b.      be calculated using a schedule of works and relevant bond equation;
                      c.      have approval of the bond calculations and amount from Council prior to lodgement;
                      d.      be lodged with Council and accompanied by the Bond Administration Fee/s; and
                      e.      be requested for release by writing to Council when relevant approval requirements
                              have been met.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               6.     Submit amended plans to Council as described by the conditions of this approval. Plans must
                      be submitted and approved prior to the pre-start meeting.
               7.     All necessary approvals from external service providers (e.g., Unitywater) and external
                      parties on which the development works are proposed have been obtained and a copy
                      supplied to Council.
               8.     Copies of the approved plans, duly signed by the consultant Registered Professional
                      Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
                      Construction at the prestart meeting.
               9.     A condition report of the drainage system and end-of-line bioretention basin must be
                      completed for agreement at the prestart meeting. The condition report is to include:
                      a.      a CCTV inspection of the existing stormwater network commencing from the end-of-
                              line bioretention basin in Ely Street and continuing to the next upstream structure from
                              “EX4/4” (as identified on the Approved Plans); and
                      b.      a dilapidation report of the existing end-of-line bioretention basin in Ely St.
               10.    A condition report including photographs of the frontage of the site must be completed and
                      submitted to council at the prestart meeting / prior to any works commencing.
               11.    Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.


                                                                                                          Page 26 of 39

Document Set ID: 23843933
Version: 14, Version Date: 05/09/2025

Used in these records

About this file

File size
1.9 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Report (Representations made) MCU24 0125, OPW24 0150 & RAL24 0021 (As Published).pdf · 1.9 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.