SARA reference: SDA-0714-012936
Applicant reference: 6520
Council reference: MCU14/0056


Date: 13 August 2014

Creekgold Pty Ltd
c/- Saunders Havill Group
9 Thompson Street
Bowen Hills QLD 4006



Dear Mr Eddie Venturini

Information request—concurrence agency
125 Myall Street, Cooroy – QLD – 4563
(Lot 4 SP248479)
(Given under section 276 of the Sustainable Planning Act 2009)

The referral agency material for the development application was received by the Department
of State Development, Infrastructure and Planning under section 272 of the Sustainable
Planning Act 2009 on 31 July 2014.

The department has carried out an initial review of the application and has determined that in
accordance with section 276 of the Sustainable Planning Act 2009, the following additional
information is requested to complete the assessment of the application:




Page 1                                                           SEQ North Region
                                                                 Level 8, Mike Ahern Building
                                                                 12 First Avenue
                                                                 PO Box 1127
                                                                 Maroochydore QLD 4558
Log in to download the original file

12936 Information Request - 125 Myall Street.pdf · 190 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 4 pages

Page 2

                                                                                     SDA-0714-012936




Item Information requested
Stormwater
1.    The proposed development is significantly increasing the impervious area of the site
      which is currently undeveloped to total site coverage of approximately 67 per cent.
      The submitted stormwater management report has briefly outlined the conceptual
      stormwater management strategy proposed to the extent of the detention required.
      However, detailed calculations are required to be supplied with the report.

          The applicant is requested to provide a stormwater report (quality and quantity) which
          assesses the potential stormwater impacts on the state controlled road networks as a
          result of the proposed development and recommends appropriate mitigation
          measures. Specifically, additional information to the currently provided stormwater
          report is required regarding the proposed method for discharging detained stormwater.

          The stormwater management plan must:
             a) Be certified by a Registered Professional Engineer of Queensland
             b) Be prepared in accordance with the Department of Transport and Main Roads’
                 Road Drainage Manual which can be accessed at
                 http://www.tmr.qld.gov.au/Business-industry/Technical-standards-
                 publications/Road-drainage-manual.aspx and with consideration given to the
                 Queensland urban Drainage manual 2013 available at
                 http://www.dews.qld.gov.au/water-supply-regulations/urban-drainage and the
                 Environmental Protection Act 1994 and Environmental Protection (Water)
                 Policy 2009 which are available at www.legislation.qld.gov.au.
             c) Demonstrate that the management of stormwater (quantity and quality) post
                 development can achieve a no worsening impact (on the predevelopment
                 condition) in accordance with the design criteria in the Department of Transport
                 and Main Roads’ Road Drainage Manual.
                 Stormwater management for the proposed development must ensure no
                 worsening or actionable nuisance to the state controlled road network caused
                 by peak discharges, flood levels, frequency/duration of flooding, flow velocities,
                 water quality, sedimentation, and scour effects.
             d) Incorporate appropriate hydraulic and hydrological analysis demonstrating:
                    design flood peak discharges for the site and surrounding area which
                        exist prior to the development for all flood and stormwater events up to a
                        1% Annual Exeedance Probability (AEP) (equivalent to 1/100 year
                        Average Recurrence Interval (ARI)). This should include at least the
                        following flood and stormwater events: 50%, 20%, 10%, 5%, 2% and 1%
                        AEP (equivalent to 2, 5, 10, 20, 50 and 100 year ARI events); and
                    design flood peak discharges for the site and surrounding area after the
                        development has occurred for all flood and stormwater events up to a
                        1% Annual Exeedance Probability (AEP) (equivalent to 1/100 year
                        Average Recurrence Interval (ARI)). This should include at least the
                        following flood and stormwater events: 50, 20, 10%, 5%, 2% and 1%
                        AEP (equivalent to 2, 5, 10, 20, 50 and 100 year ARI events).




Department of State Development, Infrastructure and Planning                         Page 2

Page 3

                                                                                  SDA-0714-012936



Item Information requested
Stormwater
         e) Ensure the following are addressed, where applicable:
               All relevant legal points of discharge for the development site are
                  identified. No new discharge points for stormwater will be permitted on
                  state controlled roads;
               The impact of existing or proposed noise barriers on overland flow paths
                  is taken into account
               Overland flow paths are identified and hydraulic conveyance is
                  maintained on the site as part of the proposed development
               Flood storage capacity is maintained on the site as part of the proposed
                  development
               The adverse impacts from sheet flow on the state controlled road
                  network are prevented
               Existing stormwater drainage infrastructure on state controlled roads is
                  not interfered with or damaged such as through concentrated flows,
                  surcharging, scour, or deposition; and
               The quality of stormwater discharging onto the state controlled road is
                  not reduced through erosion and sedimentation.
         f) Include details of the mitigation measures proposed to address any potential
            stormwater (including flooding impacts) of the proposed development.

Under section 278 of the Sustainable Planning Act 2009, when responding to this request you
must advise whether you are supplying all of the information requested, part of the information
requested, or none of the information requested. If you are supplying part or none of the
information requested, you are also required to provide written notice asking the department to
proceed with the assessment of the application.

The due date for receipt of this information is 6 months after the day you receive this request.
If necessary you may request an extension to this period. Unless a response to this request for
further information has been received from you within this period or any extension during this
period, your application will lapse.

A pro forma is attached to this notice to assist you in providing an information request
response which complies with the requirements of the Sustainable Planning Act 2009.

Please be advised that the application will be assessed on the basis of the information
provided. It is therefore recommended that you respond to all of the information requested by
the department. Further details regarding the information request response period and the
lapsing of development applications are set out in sections 279 and 280 of the Sustainable
Planning Act 2009.




Department of State Development, Infrastructure and Planning                      Page 3

Page 4

                                                                                 SDA-0714-012936


Your response to the information request must be submitted to the department through
MyDAS or alternatively emailed to [email protected] the department is a concurrence agency, you must also give a copy of the information
request response to the assessment manager under section 278(2) of the Sustainable
Planning Act 2009.

If you require any further information, please contact Tracey Smith, Senior Planning Officer,
on 3882 8409, or via email [email protected], who will be pleased to
assist.

Yours sincerely




Garth Nolan
Manager (Planning)

cc:        Noosa Shire Council




Department of State Development, Infrastructure and Planning                     Page 4

Page 5

                                                                                              SDA-0714-012936


SARA reference: SDA-0714-012936
Applicant reference: 6520
Council reference: MCU14/0056


Attn: [email protected]



Response to information request—concurrence agency
(Given under section 278 of the Sustainable Planning Act 2009)

Street address:                                       125 Myall Street, Cooroy – QLD – 4563

Real property description:                            4 SP248479

Assessment manager reference: MCU14/0056

Local government area:                                Noosa Shire Council



As the applicant of the above development application, I am responding to your information
request by:

          Enclosing all of the information requested.

          Enclosing part of the information requested and asking that the requesting authority
          proceed with the assessment of the application.
          Advising that I do not intend to supply any of the information requested and asking
          that the requesting authority proceed with the assessment of the application.



Name of applicant:                       Creekgold Ltd c/o Saunders Havill Group




Signature of applicant:

Date:




Department of State Development, Infrastructure and Planning                                  Page 5

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.