12936 Information Request - 125 Myall Street
Attached to the e-mail MCU14/0056 SARA Information request.
SDA-0714-012936
Item Information requested
Stormwater
1. The proposed development is significantly increasing the impervious area of the site
which is currently undeveloped to total site coverage of approximately 67 per cent.
The submitted stormwater management report has briefly outlined the conceptual
stormwater management strategy proposed to the extent of the detention required.
However, detailed calculations are required to be supplied with the report.
The applicant is requested to provide a stormwater report (quality and quantity) which
assesses the potential stormwater impacts on the state controlled road networks as a
result of the proposed development and recommends appropriate mitigation
measures. Specifically, additional information to the currently provided stormwater
report is required regarding the proposed method for discharging detained stormwater.
The stormwater management plan must:
a) Be certified by a Registered Professional Engineer of Queensland
b) Be prepared in accordance with the Department of Transport and Main Roads’
Road Drainage Manual which can be accessed at
http://www.tmr.qld.gov.au/Business-industry/Technical-standards-
publications/Road-drainage-manual.aspx and with consideration given to the
Queensland urban Drainage manual 2013 available at
http://www.dews.qld.gov.au/water-supply-regulations/urban-drainage and the
Environmental Protection Act 1994 and Environmental Protection (Water)
Policy 2009 which are available at www.legislation.qld.gov.au.
c) Demonstrate that the management of stormwater (quantity and quality) post
development can achieve a no worsening impact (on the predevelopment
condition) in accordance with the design criteria in the Department of Transport
and Main Roads’ Road Drainage Manual.
Stormwater management for the proposed development must ensure no
worsening or actionable nuisance to the state controlled road network caused
by peak discharges, flood levels, frequency/duration of flooding, flow velocities,
water quality, sedimentation, and scour effects.
d) Incorporate appropriate hydraulic and hydrological analysis demonstrating:
design flood peak discharges for the site and surrounding area which
exist prior to the development for all flood and stormwater events up to a
1% Annual Exeedance Probability (AEP) (equivalent to 1/100 year
Average Recurrence Interval (ARI)). This should include at least the
following flood and stormwater events: 50%, 20%, 10%, 5%, 2% and 1%
AEP (equivalent to 2, 5, 10, 20, 50 and 100 year ARI events); and
design flood peak discharges for the site and surrounding area after the
development has occurred for all flood and stormwater events up to a
1% Annual Exeedance Probability (AEP) (equivalent to 1/100 year
Average Recurrence Interval (ARI)). This should include at least the
following flood and stormwater events: 50, 20, 10%, 5%, 2% and 1%
AEP (equivalent to 2, 5, 10, 20, 50 and 100 year ARI events).
Department of State Development, Infrastructure and Planning Page 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.