Decision Notice OPW23 0179 · OPW23/0179

of 14

Text shows just the words. Original shows the document exactly as it was published.

               48.    All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
                      Council’s relevant Planning Scheme Policy prior to plan sealing. To achieve ‘On
                      Maintenance’, the supervising RPEQ must submit to Council:
                      a.      certification that all works have been undertaken and completed in accordance with the
                              requirements of this Permit.
                      b.      as Constructed details in accordance with Council’s Planning Scheme Policy.
                      c.      maintenance and operational manuals for all proprietary or site specific devices
                      Off Maintenance
               49.    Prior to requesting an Off Maintenance inspection the developer must provide a written
                      request for the Off Maintenance inspection.
               50.    A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
                      where:
                      a.      a Council inspection reveals works do not comply with approval requirements
                      b.      submitted certification falsely states works comply with approval requirements.
               5.     REFERENCE DOCUMENTS

                      The following plans require amendment.

                           Plan No.           Rev.    Plan/Document Name                            Date

                           ADG1535.23         0       Dewatering Management Plan                    31.05.2023

                           Amendments         Prior to the Prestart Meeting, submit and have approved by Council
                                              an amended Dewatering and Acid Sulfate Management Plan. The
                                              document is to be prepared and certified by a suitably qualified
                                              Registered Professional Engineer Queensland (RPEQ) and
                                              demonstrate how Acid Sulfate affected water encountered during
                                              excavation will be treated and disposed of. The following specific
                                              amendments are to be included:
                                              1. The DMP states that the shoring design is provided in Appendix
                                                 C – however only the civil engineering plans are provided.
                                                 Include plans which show the location and type of temporary
                                                 shoring, groundwater spears, treatment and monitoring
                                                 equipment location and space requirements. Why do the
                                                 structural engineering plans (provided separately) only show
                                                 shoring on 3 sides of the excavation? The type of CFA piling
                                                 (contiguous or secant) should also be stated on plan.
                                              2. Remove references to ‘steel sheet piling’ on page 10 and refer to
                                                 CFA secant piling. Please note that the references should reflect
                                                 the proposed method or the alternate method chosen by the civil
                                                 engineer.
                                              3. Update section 6.5.2 and 6.5.3 (Water Quality Monitoring) to
                                                 include continuous monitoring of pH and dissolved oxygen at the
                                                 release point from the treatment system. Total iron and
                                                 aluminium are to be sampled where identified in the document
                                                 as ‘if required’.
                                              4. Update the figure in Appendix A to also show the stormwater
                                                 network and specifically the stormwater pit which the dewatering
                                                 system will discharge into and the outlet headwall.
                                              5. Update section 6.4.3 to identify that discharge is to the
                                                 stormwater network prior to entering the canal system.
                                              6. There seems to be plenty of room in the frontage of the site for
                                                 establishing a groundwater monitoring bore outside of the


                                                                                                      Page 10 of 14
Document Set ID: 22929254
Version: 3, Version Date: 05/04/2024

Used in these records

About this file

File size
194 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice OPW23 0179.pdf · 194 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.