Decision Notice OPW23 0179 · OPW23/0179
excavation and shoring system in which to monitoring
groundwater drawdown and quality. Update the monitoring
section of the DMP to incorporate such a monitoring location.
7. Section 7 (Noise) is to be updated to refer to the default noise
standard for pumps in Section 440T of the EPA Act. The EEP
(Noise) objectives currently referenced are long-term objectives
rather than a specific enforceable standard.
8. Provide dilapidation reports for neighbouring properties and any
other structures or infrastructure identified as being within the
estimated cone of depression associated with the groundwater
drawdown.
Note: Refer to the Acid Sulfate Soils Overlay Code and PSP8 –
Natural Hazards for guidance on Acid Sulfate Soils requirements.
6. REFERRAL AGENCIES
Not applicable.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
General Advisory Notes
1. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
2. Council reserves the right to call up any performance bond held or levy charges against the
property, should emergency works be required to be undertaken by Council to make the site
safe due to inactivity on the development site for extended periods of time.
3. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Planning Act
2016 must be made. Amended plans clearly indicating the changes must be lodged with this
application along with the appropriate fees.
Prestart, On and Off Maintenance Inspections Request
4. Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
business days notice of preferred inspection time.
5. If Council officers are required to undertake additional inspections of the same works, a
reinspection fee will be applicable in accordance with Council’s Fees and Charges register
applicable at the time.
6. A minimum maintenance period of 12 months will apply to all municipal works and thereafter
until such time as the works are performing in accordance with the approved design unless
noted otherwise.
Environmental Advisory Notes
7. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Landscaping - Qualified Person
Page 11 of 14
Document Set ID: 22929254
Version: 3, Version Date: 05/04/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records