Decision Notice OPW23 0179 · OPW23/0179

of 14

Text shows just the words. Original shows the document exactly as it was published.

               8.     Qualified Person, for the purpose of:
                      a.      Supervising landscape works and preparing a landscape certification, is considered to
                              be a landscape architect, landscape designer or horticulturist with a minimum of three
                              years current experience in the field of landscape design.
                      b.      Undertaking landscape construction and establishment works is considered to be a
                              person with five years current experience in commercial landscape construction
                      c.      Undertaking, supervising tree works and preparing arboriculture certification, is
                              considered to be a person with a minimum three years current experience in tree
                              protection, hazard identification/mitigation and AS2303 Tree stock for landscape use
                              assessment and either:
                              i.       International Society of Arboriculture (ISA) certification; or A Diploma of
                                       Arboriculture
                      Erosion and Sediment Control
               9.     Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control.
               10.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               11.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •    appropriate for slopes and slope lengths; and
                              •    are consistent with best practice environmental management practices such as in
                                   the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                              If at the time of request for plan sealing, the method of short-term stabilisation has not
                              achieved a level of stability that Council's Officers believe will have a high probability
                              of achieving long term stability (i.e. until house construction has occurred on all lots),
                              Council Officers may take the following matters into consideration in determining
                              whether the site is capable of achieving medium to long-term stability:
                              •    evidence that the site has been effectively stabilised in the short term;
                              •    evidence that soil has been adequately ameliorated;
                              •    evidence that seed of annual and perennial grass species has been applied at an
                                   adequate rate; and
                              •    that grass seed has germinated at a density that is likely to achieve an effective
                                   grass cover.
                              For example, while hydromulch can provide an immediate and effective stabilising
                              cover to soils, the protective cover can be relatively short-lived if vegetation fails to
                              establish before the thin layer of mulch decomposes. So if hydromulch is selected as
                              the method of temporary short term stabilisation, Council Officers will seek to confirm
                              that perennial as well as annual grasses are well established at the time of plan sealing
                              to reduce the risk of instability of the site in the medium to long term. As a general rule,
                              hydromulch will only be accepted as a “patch” fix and should comprise no more than
                              20% of the exposed site area due to the high risk of failure. Due to the requirement to
                              progressively stabilise exposed areas, it is not envisioned that this will present any
                              difficulties for an appropriately managed and compliant site.
               8.     PROPERTY NOTES

               Not applicable.


                                                                                                          Page 12 of 14
Document Set ID: 22929254
Version: 3, Version Date: 05/04/2024

Used in these records

About this file

File size
194 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice OPW23 0179.pdf · 194 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.