Decision Notice OPW23 0179 · OPW23/0179

of 14

Text shows just the words. Original shows the document exactly as it was published.

                      h.      Provide dilapidation reports for neighbouring properties and any other structures or
                              infrastructure identified as being within the estimated cone of depression associated
                              with the groundwater drawdown.
                      Note: Refer to the Acid Sulfate Soils Overlay Code and PSP8 – Natural Hazards for guidance
                      on Acid Sulfate Soils requirements.
               4.     All necessary approvals from external service providers (e.g. Unitywater, Energex) and
                      external parties on which the development works are proposed have been obtained and a
                      copy supplied to Council.
               5.     Copies of the approved plans, duly signed by the consultant Registered Professional
                      Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
                      Construction at the “prestart” meeting.
               6.     A condition report of the drainage system must be completed for agreement at the prestart
                      meeting. The condition report is to include a CCTV inspection of the existing pipe and must
                      include at least 50m upstream and downstream of all works.
               7.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to council at the prestart meeting / prior to any works commencing.
               8.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               9.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Landscape works;
                      c.      Electrical reticulation works;
                      d.      Erosion and sediment control works;
                      e.      Other relevant parties
               10.    A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction.
                              ii.      Maintenance of safe vehicle and pedestrian access across the frontage of the
                                       site both during daily construction and after daily construction has ceased
                              iii.     Proposed fencing to the site during the construction phase of the development
                              iv.      Adequate parking arrangements for construction workers, deliveries, and other
                                       vehicles (i.e., drilling rigs, concrete trucks).
                              v.       No queuing of trucks is permitted on residential streets, especially prior to
                                       7.00am. Further parked trucks must have engines turned off
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures
                      c.      Works programme identifying key components of the works and their respective
                              durations
                      d.      Establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic and services and other relevant issues


                                                                                                        Page 4 of 14
Document Set ID: 22929254
Version: 3, Version Date: 05/04/2024

Used in these records

About this file

File size
194 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice OPW23 0179.pdf · 194 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.