Response to information request (rec. 4.9.25) MCU25-0060 · MCU25/0060
6. Provide a site specific stormwater management plan for the proposed
development. The SWMP must be prepared by a suitably qualified Registered
Professional Engineer of Queensland and include but is not limited to:
a. Stormwater runoff collection both during the construction phase
and the operational phase of the development
b. On site disposal of stormwater runoff that is consistent with the
recommendations of the site specific geotechnical investigation
and report
7. Provide a preliminary design plan for the access driveway. The plan must be
prepared by a suitably qualified Registered Professional Engineer of
Queensland and include but is not limited to:
c. Levels and grades of the existing common property road and the
transitions to the residential driveway
d. A longitudinal section extending from the common property road
to the garage floor including sufficient detail that demonstrates
that a vehicle will not bottom out or scrape on the common
property road or the driveway when entering and exiting the site.
e. Any necessary drainage grates to collect surface runoff
Westera Engineers provide a stormwater management plan and design for the access
driveway, demonstrating a compliant driveway gradient. All engineering reports have been
coordinated and updated with the revised architectural plans.
Page 4 of 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to information request (rec. 4.9.25) MCU25-0060.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.