Attachment C - Copy of 2019 Approval - Decision Notice · MCU19/0049.01
Damage to infrastructure
64. Any damage to footpaths, street plantings, natural vegetation/trees kerb and channel,
bridges or roadways must be repaired or reinstated to at least pre-existing conditions.
Vacant site
65. The site must be left clean and tidy free from debris such as concrete, wire, rubble, brick/s
and the like. If the site remains vacant for more than 30 days the lot/s must be turfed or
landscaped in accordance with Planning Scheme Policy PSP 3 – Landscaping Plants and
Guidelines and to the satisfaction of Council so as to not cause nuisance to the surrounding
area.
66. All waste materials must be removed from site.
Litter, erosion and sediment control
67. Litter, erosion and sediment control measures must be installed and maintained until soils
are stabilised by turf, vegetation or sealed.
Note: it is an offence under the Environmental Protection Act 1994 to deposit or potentially
allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
system (e.g. roadside gutter).
Asbestos
68. Removal of building materials containing asbestos must be undertaken by a licensed
asbestos removalist.
69. Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
requires a licensed asbestos removalist to give notice to Workplace Health and Safety
Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
commences. Notification must be made using Form 65: Notification of licensed asbestos
removal work, demolition work or emergency demolition.
70. All building materials containing asbestos products are wrapped and disposed of in
accordance with the Public Health Regulation 2006 and the Environmental Protection
Regulation 2008.
Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
businesses that transport asbestos waste, and landfills that accept this waste.
71. All building materials containing asbestos, including asbestos cement sheeting or roofing and
lagging are removed from the building prior to demolition/relocation.
Plumbing and Drainage
72. It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2003’ that at
demolition of a building, the existing sanitary drain upstream from the connection point for a
service provider’s sewerage system must be sealed water tight. This work is deemed as
notifiable Work and must be carried out by a suitably licenced plumber who must submit an
As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
Construction Commission) within 10 days of completing the work.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Page 10 of 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment C - Copy of 2019 Approval - Decision Notice.pdfRelated documentApplication case desk ↗
About this file
- File size
- 451 KB (small file)
- File type
No other editions are linked here.